In a lump sum
contract, the owner has essentially assigned all the risk to the contractor, who in turn can be expected to ask
for a higher markup in order to take care of unforeseen contingencies. Beside the fixed lump sum price, other commitments are often made by the
contractor in the form of submittals such as a specific schedule, the management reporting system or a quality
control program. If the actual cost of the project is
underestimated, the underestimated cost will reduce the contractor’s profit by that amount. An overestimate has an opposite effect, but may reduce the chance of being a
low bidder for the project.
Unit Price
Contract
In a unit price
contract, the risk of inaccurate estimation of uncertain quantities for some key tasks has been removed from the
contractor. However, some contractors may submit an “unbalanced
bid” when it discovers large discrepancies between its estimates and the owner’s estimates of these
quantities. Depending on the confidence of the contractor on its
own estimates and its propensity on risk, a contractor can slightly raise the unit prices on the underestimated
tasks while lowering the unit prices on other tasks. If the
contractor is correct in its assessment, it can increase its profit substantially since the payment is made on
the actual quantities of tasks; and if the reverse is true, it can lose on this basis. Furthermore, the owner may disqualify a contractor if the bid appears to be
heavily unbalanced. To the extent that an underestimate or
overestimate is caused by changes in the quantities of work, neither error will affect the contractor’s profit
beyond the markup in the unit prices.
For certain
types of construction involving new technology or extremely pressing needs, the owner is sometimes forced to
assume all risks of cost overruns. The contractor will receive the
actual direct job cost plus a fixed percentage, and have little incentive to reduce job cost. Furthermore, if there are pressing needs to complete the project, overtime
payments to workers are common and will further increase the job cost. Unless there are compelling reasons, such as the urgency in the construction
of military installations, the owner should not use this type of contract.
Cost Plus Fixed
Fee Contract
Under this type
of contract, the contractor will receive the actual direct job cost plus a fixed fee, and will have some
incentive to complete the job quickly since its fee is fixed regardless of the duration of the
project. However, the owner still assumes the risks of direct job
cost overrun while the contractor may risk the erosion of its profits if the project is dragged on beyond the
expected time.
Cost Plus
Variable Percentage Contract
For this type
of contract, the contractor agrees to a penalty if the actual cost exceeds the estimated job cost, or a reward
if the actual cost is below the estimated job cost. In return for
taking the risk on its own estimate, the contractor is allowed a variable percentage of the direct job-cost for
its fee. Furthermore, the project duration is usually specified and
the contractor must abide by the deadline for completion. This type
of contract allocates considerable risk for cost overruns to the owner, but also provides incentives to
contractors to reduce costs as much as possible.
Target Estimate
Contract
This is another
form of contract which specifies a penalty or reward to a contractor, depending on whether the actual cost is
greater than or less than the contractor’s estimated direct job cost. Usually, the percentages of savings or overrun to be shared by the owner and
the contractor are predetermined and the project duration is specified in the contract. Bonuses or penalties may be stipulated for different project completion
dates.
Guaranteed
Maximum Cost Contract
When the
project scope is well defined, an owner may choose to ask the contractor to take all the risks, both in terms of
actual project cost and project time. Any work change orders from
the owner must be extremely minor if at all, since performance specifications are provided to the owner at the
outset of construction. The owner and the contractor agree to a
project cost guaranteed by the contractor as maximum. There may be
or may not be additional provisions to share any savings if any in the contract. This type of contract is particularly suitable for turnkey
operation.
It is the fate of the Property Manager to toil at the lower
employments of life; to be rather driven by the fear of evil than attracted by the prospect of good; to be
exposed to censure without hope of praise; to be disgraced by miscarriage or punished by neglect, where
success would have been without applause and diligence without reward. While others may aspire to praise, the
Property Manager can only hope to escape reproach, and even this negative recompense has yet been granted to
very few.
HOA Board Members may request log-in information to our Members Only area, which is packed with lots of very unseful information cannot be found anywhere else
on the web
As Property
Managers, we all have learned primarily
through our mistakes
and pursuits of false assumptions
rather than by our exposure
to fountains of wisdomand