Construction Prompt Payment Laws
With private
construction at its slowest pace in
years and public construction wavering as government budgets are cut, contracting parties in the construction
industry are learning the importance of how they label payments. A
payment may look like a progress payment—which by law is required to be paid within a specified number of
days—or it may seem to be a retention—which by law is required to be paid upon completion of
work. California has a collection of laws known as the prompt
payment statutes that are supposed to guarantee that contractors and subcontractors will be paid promptly for
the work they perform. Nevertheless, California courts of appeal
have news for contractors: If they do not carefully and precisely name payments and spell out when and under
what circumstances payments are due, contractors may not be able to obtain the penalties and interest
otherwise available when payments are late.
Payments are always an issue
in construction projects, and this is especially so in tough economic times. The speed of the flow of money from lender to owner to contractor becomes
slower as the ability to borrow tightens. Profit margins shrink as
contractors and subcontractors cut their bids in order to compete for what work is available.
Everyone in the payment chain
wants to hold on to cash for as long as possible, with the result that many smaller contractors and
subcontractors complain that they are being forced to wait longer and longer for payments that should have been
made more promptly. They in turn cannot pay their employees or for
supplies—and in today’s financial climate, borrowing may not be an option. However, recent state appellate decisions have cut back on the protections
that the prompt payment statutes were meant to provide.
The current economic downturn
in the construction industry is similar to the losses it endured in the 1980s, with smaller contractors and
subcontractors bearing the brunt of the pain. The industry had
fallen into the practice of slow payments in both public and private construction arenas. Prior to the 1990s contractors and subcontractors had limited remedies at
their disposal when progress payments or retentions were withheld.
Contractors complained that owners would hold retentions for open-ended periods of time. Subcontractors complained that they did not receive progress payments on
time.
Generally, the terms of
payment to contractors and subcontractors in California were determined by the contract or subcontract
documents.
The party with the greatest
leverage—generally an owner vis-à-vis a contractor or a contractor vis-à-vis subcontractors—was able to draft
contractual provisions providing for slow progress payments and large retentions. During lean times with tight credit, subcontractors were forced to obtain
loans in order to manage cash flow, especially when retentions were held for a long time and, as is often the
case in depressed markets, when the retention equaled or exceeded their profits. It had become commonplace for owners to withhold money from general
contractors and general contractors to withhold money from subcontractors—and then dare the other party to
sue.
Legislative
Response
In 1990,
following a period of losses and bankruptcies, the California Legislature took action and passed Senate Bill
2515, the first of a series of prompt payment statutes designed to provide meaningful protection to contractors
and subcontractors. The legislative history of Senate Bill 2515
makes clear that the lawmakers recognized a problem in need of a remedy: “Slow payment or nonpayment to
subcontractors is one of the more serious problems facing the construction industry.” Senate Bill 2515, codified as Civil Code Section 3260, requires prompt payment
of retentions by owners and general contractors on private works construction. Two years later, the legislature established Public Contracts Code Section
7107 to extend the protections of the prompt payment requirements to public works construction. The section requires a public entity to pay retention to the original
contractor within 60 days after the date of completion. Further,
original contractors must pay subcontractors their retention within seven days from the receipt of funds from a
public entity.
The legislature
followed these enactments with a number of other statutes:
• Civil Code
Section 3260.1 requires owners to pay prime contractors progress payments within 30 days of a contractor’s
request for payment.
• Business and
Professions Code Section 7108.5 requires prime contractors or subcontractors to pay all tiers of subcontractors
within 10 days of receipt of funds by contractors for private projects. Public Contract Code Section 10262.5 makes the requirement applicable to
contractors and subcontractors in public works construction.
• Public
Contract Code Section 10261.5 requires that state agencies pay the prime contractors within 30 days after a
payment request or engineer submittal.
• Civil Code Section 3320
requires any public entity to pay a design professional within 30 days of the design professional’s demand if it
is for a progress payment and within 45 days if retention is due.
Civil Code Section 3321 requires a design professional to pay both progress and retention payments to the design
professional’s subconsultants within 15 days after receipt from the public agency.
• Public Contract Code
Section 7200 limits the amount of retentions that may be withheld in public works construction.
These prompt payment
statutes, among others, prescribe remedies for late payment in the form of penalties in addition to interest in
some cases, penalties in lieu of interest in other instances, and often costs of suit and attorney’s fees to the
prevailing party. California’s contractors and subcontractors would
seem quite well protected when it comes to being paid promptly.
Prompt payment statutes are
common around the country. In addition, in 1982 Congress passed a
federal prompt payment act partly as a result of a General Accounting Office report finding that government
agencies were late in paying 30 percent of their bills. All states,
with the exception of New Hampshire, have some form of prompt payment legislation applicable to government
contracts; many states also have prompt payment laws that apply to private construction.
California
seems to have more prompt payment statutes in place than any other jurisdiction. However, at a time when contractors and subcontractors need them the most, the
protections of these statutes are proving illusory in many cases.
Recent Appellate
Decisions
The California
Legislature enacted prompt payment statutes to ensure that contractors and subcontractors will be paid promptly
for the work they perform. Three recent state appellate court
decisions, however, have interpreted the prompt payment statutes in a manner that restricts the applicability of
their provisions. In each case, the court’s interpretation, while
arguably defensible in terms of strict statutory construction without reference to legislative history, is at
odds with the original intention of the prompt payment legislation.
In Martin
Brothers Construction, Inc. v. Thompson Pacific Construction, Inc., the Third District Court of Appeal dealt
a blow to two of the statutory protections encompassed under the prompt payment statutes. First, the court held that the statutory exception allowing a contractor to
withhold retention when there is a “bona fide dispute” did not apply only to a bona fide dispute relating to the
contract payments. Rather, the court held that a contractor could
withhold retention after the subcontractor raised a dispute relating to change orders outside the contract, even
though the contractor had no dispute regarding the work performed under the contract. Second, the court affirmed the right of contractors to include language in the
subcontract that amounted to a waiver of certain protections of the prompt payment provisions.
In that case, the plaintiff
subcontractor, Martin Brothers Construction, brought an action against a general contractor, Thompson Pacific
Construction, and against the general contractor’s surety and bonding companies. Martin Brothers sought penalties, interest, and attorney’s fees for late
progress and retention payments for work on a public works project.
The subcontract provided that Thompson would make monthly progress payments to Martin Brothers, minus a
retention. Also, the subcontract contained a provision that neither
the progress payments nor the withheld retention would be paid until Martin Brothers had furnished specified
documentation, including lien releases, certified payroll, union letters, and proof of
insurance.
For final payment of the
previously withheld contract retention, the subcontract required additional releases. Martin Brothers did not provide the specified documentation promptly, and
Thompson Pacific accordingly did not pay Martin Brothers within the statutory time limits. Moreover, at the conclusion of the project, the contractor withheld the
retention amounts—even though it acknowledged that all the contracted work had been performed—based on disputes
between the parties involving change orders for additional work.
Martin Brothers made claims under both Business and Professions Code Section 7108.5 (progress payments) and
Public Contract Code Section 7107 (retention payments).
Under Public Contract Code
Section 7107, the failure of a contractor to pay a subcontractor within seven days of a contractor being paid by
the public entity allows the subcontractor to receive a penalty payment of 2 percent per month on the amount
withheld. The subcontractor also is entitled to attorney’s
fees. The section expressly states that any waiver of this
requirement is void as against public policy.
Nevertheless, Section 7107(e)
contains an exception: “The original contractor may withhold from a subcontractor its portion of the retention
proceeds if a bona fide dispute exists between the subcontractor and the original
contractor. The amount withheld from the retention payment shall
not exceed 150 percent of the estimated value of the disputed amount.”
The court in Martin
Brothers Construction recognized that Section 7107 “serves a remedial purpose: to encourage general
contractors to pay timely their subcontractors and to provide the subcontractor with a remedy in the event that
the contractor violates the statute.”
Nonetheless, the court
refused to construe Section 7107 liberally in light of this remedial purpose and limit withholding of contract
retention proceeds due to a bona fide dispute related to the contract work. The court held instead that the word “dispute” in Section 7107 was not limited
to any particular kind of disputes other than those that are bona fide. Accordingly, the court deprived the subcontractor of the right to prompt
payment of the contract retention, notwithstanding the fact that the contractor had no dispute regarding the
subcontractor’s performance on the contract.
The court also addressed the
meaning of the phrase “unless otherwise agreed to in writing” as a qualification to the rule in Business and
Professions Code Section 7108.5 requiring prompt payment of progress payments. Section 7108.5 provides that a “prime contractor or subcontractor shall pay to
any subcontractor, not later than 10 days of receipt of each progress payment, unless otherwise agreed to in
writing, the respective amounts allowed the contractor on account of the work performed by the subcontractors,
to the extent of each subcontractor’s interest therein.” The trial
court and court of appeal found that Thompson Pacific and Martin Brothers had “otherwise agreed” to a different
time of payment. Thus the parties had “opted out” of Section 7108.5
by the provision in the subcontract that stated, “Subcontractor agrees that payment is not due until
Subcontractor has furnished all applicable administrative documentation required by the contract documents and
the applicable releases pursuant to Civil Code section 3262.” The
court interpreted the language of Section 7108.5 to permit contractors and
subcontractors to waive the payment requirements otherwise provided for in that statute, perhaps even
indefinitely.
It is true that
Section 7108.5 permits parties to “otherwise agree in writing.” The
parties may wish to agree to lump sum payments upon conclusion of certain construction milestones, for
example. However, the court of appeal’s holding in Martin
Brothers Construction has now opened the door for contractors to incorporate language into subcontracts
under Section 7108.5 that authorizes indefinite delay. Although
several of the prompt payment statutes expressly prohibit waiver of the protections as against public policy,
Section 7108.5 does not contain such an express prohibition.
Final Payment or Progress
Payment
In Murray’s
Iron Works, Inc. v. Boyce, the Sixth District Court of Appeal dealt with the question of whether a final
payment, due at the conclusion of the work, was covered by Civil Code Section 3260.1,which provides for prompt
payment of progress payments. According to Section 3260.1(b),
“Except as otherwise agreed in writing, the owner shall pay to the contractor, within 30 days following
receipt of a demand for payment in accordance with the contract, any progress payment due thereunder as to which
there is no good faith dispute between the parties.” Civil Code
Section 3260(g) further provides that the remedy for failing to make a progress payment when due is the same
remedy as provided under Section 3260 covering retentions—namely, a charge of 2 percent per month on the
improperly withheld amount, in lieu of any other interest, as well as attorney’s fees and costs to the
prevailing party.
The contract in Murray’s
Iron Works provided that payment would be made “50% Deposit/Net upon Satisfactory Completion of
Project.” Upon completion, the owner paid less than half of the
outstanding amount ($50,000 of $116,222) and raised a claim of breach of contract as a result of the contractor
providing decorative ironwork containing imitation gold leaf rather than 22-carat gold leaf. Contending that imitation gold leaf was agreeable to the parties as an
acceptable finish, the contractor sued under Civil Code Section 3260.1 for the remainder of the final
payment. In construing Section 3260.1, the court stated, “Since the
payment was not due until the project was completed, it is considered a final payment and not a progress
payment.” While the term “progress payment” is not defined anywhere
in the Civil Code, the Business and Professions Code defines “progress payments” as “any payments, other than
the down payment,…made before the project is completed.” Sections
10853(e)(1) and 20104.50 of the Public Contracts Code define “progress payments” as “all payments due
contractors, except that portion of the final payment designated by the contact as retention
earnings.” From these analogous sources, the court of appeal in
Murray’s Iron Works reasoned that at least part of a final payment could be deemed a progress
payment.
Nevertheless, the court came
to the “logical conclusion” that inasmuch as a final payment is to be made after all work is completed, that
payment cannot be a progress payment because “there is nothing left on which to stop work.” The contractor may have thought that its final progress payment was protected
under the prompt payment provisions of Section 3260.1, but by failing clearly to name that payment a progress
payment, the contractor lost its remedy.
The Second District Court of
Appeal also addressed the final payment issue in Yassin v. Solis. Following Murray’s Iron Works, the Yassin court agreed that a
final payment was not a progress payment. Moreover, the court held
that the final payment also was not a retention payment under Section 3260: “The remedy for the failure to pay a
last installment payment upon completion of the services is simply damages for a breach of
contract.”
Yassin, a contractor, was
hired by the Solises to do improvement work on their home. The
contract for $75,000 provided for a down payment and additional payments at various stages of construction,
including $15,000 after the final inspection and a final payment of $7,500 due upon the issuance of the
certificate of occupancy. The trial court awarded Yassin nothing on
his claim and awarded the Solises $50,000 on their cross-complaint for deficient work. In addition, the trial court awarded the Solises attorney’s fees on the theory
that they had prevailed on Yassin’s claim for the final $7,500 payment—which the trial court deemed to be a
retention under Section 3260.
The court of appeal reversed
the award of attorney’s fees on the ground that the final payment was not a retention payment, and thus Section
3260 was not applicable.
In reaching this result, the
Yassin court reasoned that the last payment did not constitute “retention proceeds withheld from any
payment” but was instead merely a final payment. The court stated,
“Retention amounts are a form of security generally retained by the owner from prior payments due for work
previously performed.” The final payment is just that, a final
payment, and not an amount that has been previously withheld, unless the contract specifies that sums were being
withheld during the course of the work. The trial court had
recognized that the final payment of $7,500 was 10 percent of the total contract price, which is the amount
usually withheld by the owner, and had deemed the final payment to be a retention because it was not to be paid
until the work was approved. While noting that this position was
“tenable,” the court of appeal rejected it, apparently because the contract did not name the final payment a
retention.
As if to confirm the
confusion and inconsistencies inherent in the collection of prompt payment statutes, the Second District
followed its decision in Yassin with another (and rather complicated) analysis of Civil Code Sections
3260 and 3260.1 in Heinerfeld-Ward, Inc. v. Lipian.21 At issue in that case was whether the contractor
was entitled to an award of attorney’s fees under Section 3260.1 as a result of the owner’s withholding of
progress payments.
The court’s analysis
demonstrates the tangled thicket that the prompt payment statutes have become: As we have seen, section 3260.1,
subdivision (b) provides for recovery of the “penalty” specified in section 3260, subdivision (g), but that
statute does not use the term “penalty.” In contrast, other prompt
pay statutes cited by the parties expressly characterize a monthly charge imposed on withheld amounts as a
“penalty.” The characterization of the monthly two percent charge
in section 3260, subdivision (g) as “in lieu of interest” rather than as a “penalty” reflects a legislative
choice to distinguish that statute from other prompt pay statutes.
Had the Legislature employed the term “penalty” in section 3260, subdivision (g) to describe the two percent
charge, the statute would not be ambiguous and no resort to other interpretive aids would have been
required.
The court despaired of
finding clarity in the statutes and turned to legislative history for support for its conclusion that both the 2
percent monthly interest payment and the prevailing party attorney’s fees were intended to be the “penalty”
within the meaning of Section 3260.1.
Naming
Payments
What is evident
from these cases is that judges are reading the prompt payment statutes narrowly and cautiously. Construction disputes traditionally are more apt to find their way into
arbitration, and as a result, the published case law on payment issues is relatively slim. The court in Martin Brothers Construction refused to take judicial
notice of the legislative history that would have explained the purpose of the prompt payment laws, stating that
the language of the statutes was clear enough for the court to interpret without the need for outside
resources. Likewise, the courts in Yassin and
Murray’sIron Works
relied upon a careful parsing of the statutory
language and compared that to the contract provisions at issue.
For counsel drafting
construction contracts, the lessons from these recent cases is the importance of carefully naming
payments. This includes not only defining what each payment is but
also denoting the preconditions to payment and when payment is due.
Progress payments and retention payments have specific statutory protections, but these payments must be clearly
specified. If a payment due at the end of construction is one last
“progress payment” (albeit at the end of the progress), it should be identified clearly as a “progress payment”
or the “final progress payment.” If the final payment is payment of
the retention, it should be named “payment of the retention.” Cats
may have three names, as T.S. Eliot has written, but payments under construction contracts are better off having
only one name—and a very specific one at that.
Owners have the greater
bargaining power in the current economic climate, but counsel for contractors should be able to specify and
clarify the conditions that must be met before payments are made.
If lien releases or other documentation are required, the contract should specify that payments are to be made
within a certain number of days after the documentation has been provided, in order to avoid an indefinite
delay. With regard to retention against disputes, the contract
should clarify the disputes against which the retention is being withheld. Owners and contractors both benefit from contract terms that are clear and
explicit.
California’s prompt payments
statutes reflect a legislative determination that contractors and subcontractors should be paid promptly for
their work. In scaling back these protections in Martin Brothers
Construction, Murray’s Iron Works, and Yassin, the courts of appeal did not dispute this
remedial statutory purpose but nonetheless applied rules of strict statutory construction. Assuming that the construction industry believes that prompt payment statutes
are still needed, the time is now for all parties involved in the industry to propose that the legislature
create a uniform statutory scheme. This would replace the current
disparate and inconsistent statutes and directly address the issues presented by the recent appellate opinions
as well as future decisions that may further restrict California’s prompt payment remedies.
|