Great West Contractors, Inc. v. WSS Industrial Construction, Inc. (2008) 162 Cal.App.4th 581, -- Cal.Rptr.3d --
[No.
B191662. Second Dist., Div. Eight. Mar. 28, 2008.]
[As
modified Apr. 28, 2008.]
GREAT
WEST CONTRACTORS, INC., et al., Defendants and Appellants, v. WSS INDUSTRIAL CONSTRUCTION, INC., Plaintiff and
Respondent.
(Superior
Court of Los Angeles County, No. BC323833, Malcolm H. Mackey, Judge.)
(Opinion
by Cooper, P.J., with Rubin, J., and Flier, J., concurring.)
COUNSEL
Pitre
& Teunisse, Inc., Carole M. Pitre and Patricia A. Teunisse for Appellant Great West Contractors, Inc.
Robins,
Kaplan, Miller & Ciresi, Edward D. Lodgen and Laura P. Nash for Appellant Fidelity and Deposit Company of
Maryland.
Hunter,
Molloy & Salcido, John Logan Hunter and David A. Delgado for Respondent WSS Industrial Construction, Inc.
[162 Cal.App.4th 585]
OPINION
COOPER,
P.J.-
SUMMARY
A
corporate subcontractor sued a general contractor to recover for work performed under a construction services
agreement. At trial, the general contractor and its surety moved for nonsuit arguing the subcontractor was
barred by the Construction Services Licensing Law, Business and Professions Code section 7000 et seq. (the
CSLL), from maintaining any action for recovery because the subcontractor was not properly licensed at all times
during its performance of the contract. The trial court disagreed. It concluded the corporation's president held
a valid individual contractor's license at all times and that, in any event, licensure was not required for
tasks the corporation performed prior to obtaining its license. The court found "there was substantial
compliance with the licensing [statute] during the contract and work was performed in good faith," and denied
the motions for nonsuit A jury found in favor of the subcontractor and awarded over $220,000 in damages,
statutory penalties and interest.
We
conclude the trial court erred in denying nonsuit. With one exception, the CSLL forbids a contractor from
recovery -- in law or at equity -- on an otherwise valid claim for performance of any service for which a
license is required if the contractor was unlicensed at any time during performance of the work. In this case,
the subcontractor was unlicensed during a period in which it performed services that could only be performed by
a licensed contractor. We further hold the subcontractor is unable to meet the threshold requirement to invoke
the statutory exception of substantial compliance with the CSLL, because it was never licensed as a state
contractor prior to beginning performance. Accordingly, we will reverse and remand the matter for entry of
judgment in favor of the general contractor and its surety.
FACTUAL
AND PROCEDURAL BACKGROUND fn.
1
Plaintiff
and respondent WSS Industrial Corporation, Inc. (WSS or, at times, "the corporation"), a steel subcontractor,
sued general contractor appellant Great West Contractors, Inc. (Great West), to recover for work WSS performed
under a subcontract with Great West for improvements on a public works project at the New Middle School for the
Deaf, in Riverside, California (the project). [162 Cal.App.4th 586]
On
August 28, 2001, WSS submitted a bid proposal to Great West to perform steel construction work on the project
for $440,000. At the time WSS submitted its bid it had applied for but had not yet obtained a corporate
contractor's license. That license was issued on December 21, 2001. The bid proposal was incorporated into a
subcontract with Great West. WSS subsequently filed this action against Great West and its surety, appellant
Fidelity and Deposit Company of Maryland (Fidelity) fn.
2 , seeking approximately $91,000 for unpaid services under the subcontract and change orders
thereto. fn.
3
A
jury trial was conducted in January 2006. After WSS rested, Great West and Fidelity moved for nonsuit, asserting
WSS was statutorily barred by the CSLL from recovery under the subcontract because it was not duly licensed at
all times during performance of the contract, and could not demonstrate substantial compliance with state
licensing requirements because the corporation never held a California contractor's license before it began work
under the subcontract. (Bus. & Prof. Code,
� 7031,
subd. (a); all further statutory references are to that code.) WSS opposed the motions. The court conducted an
evidentiary hearing on the licensing issue and WSS's claim that it substantially complied with the CSLL, and took
the matter under submission. Ultimately, it denied the motions for nonsuit. It concluded that WSS's president,
Henry Ramirez, held valid individual licenses at all times and that, in any event, licensure was not required for
certain tasks WSS performed before December 21, 2001. The court held "there was substantial compliance with the
licensing during the contract and work was performed in good faith." The matter proceeded. The jury returned a
special verdict in favor of WSS, which was ultimately awarded approximately $220,000 in contract damages, statutory
penalties and interest. This appeal follows the denial of appellants' posttrial motions for a new trial, vacation
of the judgment, fn.
4 and/or judgment notwithstanding the verdict.
DISCUSSION
Great
West insists the trial court erred in denying nonsuit because there can be no question WSS, the corporate
entity, was not licensed, as required by section 7031 of the CSLL, at all times during its performance of the
construction services agreement it seeks to enforce. And, because WSS was not duly licensed and cannot satisfy
the strict requirements of the statutory substantial compliance exception, Great West contends WSS is barred
from [162 Cal.App.4th 587] maintaining this action, regardless of its merits, and from any recovery at
law or in equity. We conclude Great West is correct. We summarize first the controlling legal principles, then
apply them to the facts of this case.
1.
The licensure requirements embody a legislative scheme aimed at protecting the public against unscrupulous
and incompetent contractors.
[1]
Since its adoption in 1939, the CSLL "has declared that, except as expressly otherwise provided, a contractor
may not sue to collect compensation for performance of 'any act or contract' requiring a license without
alleging that he or she was duly licensed 'at all times during the performance of that act or contract.' "
(MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co., Inc. (2005)
36 Cal.4th 412,
425 (MW Erectors), citing
� 7031,
subd. (a), and Stats. 1939, ch. 37,
� 1,
p. 381.) "[T]he bar extends to actions 'in law or equity' and applies 'regardless of the merits of the cause of
action.' [Citation.]" (Ibid.)
[2]
The CSLL embodies a comprehensive legislative scheme governing the construction business in California. It
reflects a strong public policy which favors protecting the public from unscrupulous and incompetent
contractors. According to our Supreme Court, "The purpose of the licensing law is to protect the public from
incompetence and dishonesty in those who provide building and construction services. [Citation.] The licensing
requirements provide minimal assurance that all persons offering such services in California have the requisite
skill and character, understand applicable local laws and codes, and know the rudiments of administering a
contracting business. [Citation.]" (Hydrotech Systems, Ltd. v. Oasis Waterpark (1991)
52 Cal.3d 988,
995 (Hydrotech); see also Construction Financial v. Perlite Plastering Co. (1997)
53 Cal.App.4th 170,
176-177 (Construction Financial).) Section 7031, subdivision (a), applies "[r]egardless of the equities."
(Hydrotech, supra, at p. 997.) For the past 50 years, it has been held that "courts may not resort to
equitable considerations in defiance of section 7031." (Lewis & Queen v. N.M. Ball Sons (1957)
48 Cal.2d 141,
152 (Lewis & Queen).) That is because the statute " ' "represents a legislative determination that the
importance of deterring unlicensed persons from engaging in the contracting business outweighs any harshness
between the parties . . . ." ' [Citations omitted.]" (MW Erectors, supra, 36 Cal.4th at p. 423.)
[3]
Section 7031, subdivision (a) requires all persons engaged in the business or acting in the capacity of a
contractor to be licensed. A contractor is defined as "any person who undertakes to or offers to undertake to,
or purports to have the capacity to undertake to, or submits a bid to, or does [162 Cal.App.4th 588]
himself or herself or by or through others, construct, alter, repair, add to, subtract from, . . . [or] improve
. . . any building . . . or other structure, project, development or improvement, or to do any part thereof . .
. , whether or not the performance of work . . . involves the addition to, or fabrication into, any . . .
project . . . of any material or article of merchandise. 'Contractor' includes subcontractor or specialty
contractor." (
� 7026.)
"Persons" engaged in the business or acting in the capacity of a contractor is broadly defined to include "an
individual, a firm, copartnership, corporation, association or other organization, or any combination of any
thereof." (
� 7025.)
[4] A corporation applying for a contractor's license must qualify through either a "Responsible Managing Officer"
(RMO) or "Responsible Managing Employee" (RME), who is him or herself, eligible for the same license qualification.
(
� 7068,
subd. (b)(3).) The "qualifier" RMO or RME must be a bona fide officer or employee of the corporation and actively
engaged in work encompassed by the license. (
� 7068,
subd. (d).)
[5]
Section 7031, subdivision (a) is the primary enforcement mechanism for the CSLL. It provides: "Except as
provided in subdivision (e), no person engaged in the business or acting in the capacity of a contractor, may
bring or maintain an action, or recover in law or equity in any action, in any court of this state for the
collection of compensation for the performance of any act or contract where a license is required by this
chapter without alleging that he or she was a duly licensed contractor at all times during the performance of
that act or contract, regardless of the merits of the cause of action brought by the person . . . ." If
licensure is controverted, the plaintiff must prove, by producing a verified certificate of licensure from the
Contractors' State License Board (the Board), that it held all necessary licenses during performance of the
work. (
� 7031,
subd. (d).)
[6]
Section 7031, subdivision (e), provides the sole exception to the contractor's licensure requirements. It
permits a court to find there has been "substantial compliance" with the licensure requirements "if it is shown
at an evidentiary hearing that the person who engaged in the business or acted in the capacity of a contractor
(1) had been duly licensed as a contractor in this state prior to the performance of the act or contract, (2)
acted reasonably and in good faith to maintain proper licensure, (3) and did not know or reasonably should not
have known that he or she was not duly licensed." (The statute was amended in 2003; those changes, not relevant
here, were nonsubstantive and declarative of existing law. See Stats. 2003, ch. 289,
� 2.)
[162 Cal.App.4th 589]
The
trend in changes to section 7031 over many years has been to severely limit the doctrine of substantial
compliance; it only applies if all three requirements of subdivision (e) are met. (Construction Financial,
supra, 53 Cal.App.4th at pp. 180, 182-183 [reviewing legislative history of section 7031]; see also
Pacific Custom Pools, Inc. v. Turner Construction Co. (2000)
79 Cal.App.4th 1254,
1261-1262 [trend of legislative changes has been to narrow available exceptions to section 7031's bar on actions by
unlicensed contractors].) The statutory policy embodied in the CSLL is intended "to discourage persons who have
failed to comply with the licensing law from offering or providing their unlicensed services for pay."
(Hydrotech, supra, 52 Cal.3d at p. 995.) "Because of the strength and clarity of this policy," the Supreme
Court has observed "section 7031 applies despite injustice to the unlicensed contractor. 'Section 7031 represents a
legislative determination that the importance of deterring unlicensed persons from engaging in the contracting
business outweighs any harshness between the parties, and that such deterrence can best be realized by
denying violators the right to maintain any action for compensation in the courts of this state. [Citation.] . . .
.' [Citations.]" (Ibid.) Thus, the issue is not whether WSS performed services under the contract for which
it should be paid. Rather, the dispositive issues are whether WSS was required to be licensed during its
performance of the subcontract or, if so, whether it may invoke the doctrine of substantial compliance.
2.
Application of legal principles to this case -- Section 7031 bars WSS's recovery because the corporation was
not properly licensed during performance of the contract.
a.
WSS performed work before it was licensed.
In
this action, WSS the corporation, entered into a subcontract with Great West. WSS was thus the "person" engaging
in the business or acting in the capacity of a contractor. Accordingly, once licensure was controverted, it was
WSS's obligation to prove the corporation was properly licensed at all times during performance of the act or
contract at issue. (
� 7031,
subd. (d).) fn.
5 It failed to do so. [162 Cal.App.4th 590]
WSS
was incorporated in April 1999. The corporation applied for a contractor's license on August 20, 2001, and
submitted its bid proposal to Great West on August 28, 2001. fn.
6 On December 1, 2001, WSS executed the subcontract, which incorporated its bid proposal. WSS
agreed to "obtain necessary licenses prior to starting work," and to "comply with all laws, rules, ordinances,
and regulations of all governing bodies having jurisdiction over the work." WSS did not obtain its contractor's
license until December 21, 2001. WSS's license expressly states it "did not exist before that date." WSS
inserted its contractor's license number and returned the subcontract to Great West in early January 2001. Great
West signed the document on January 2, 2002.
Meanwhile,
on October 10, 2001, WSS notified the state (the owner of the project) it intended to begin work on the project
within 20 days. That notice was required so the corporation could be paid for its work. On October 29, 2001, WSS
sent Great West an invoice for $15,000 for initial preparation of "shop drawings." Ramirez testified the invoice
was for work to be completed by the corporation by October 31, 2001. WSS submitted a second invoice for $11,000
on December 19, 2001, "for work completed to date," which included $9,000 for shop drawings and $2,000 for
specialized anchor bolts WSS ordered and had delivered to the project. Ramirez testified that ordering materials
-- such as anchor bolts -- was included in WSS's subcontract. He also testified he knew licensure was required
for preparation of shop drawings, and that he knew WSS did not have its contractor's license when it submitted
its first two invoices. WSS sent Great West a third invoice on December 25, 2001. That invoice sought payment
for about $192,000 worth of materials, including 40 percent each of the Canopies/Steel and Tube Steel
Columns/Steel, 80 percent of the Canopies/Galvanize and 100 percent of the Rolling Tube Steel. Each of these
items was included in WSS's bid proposal. The December 25 invoice included work WSS expected to complete and
have inspected by December 31, 2001. fn.
7 [162 Cal.App.4th 591]
WSS
was not duly licensed at all relevant times. WSS was unlicensed when it submitted its first two invoices for
work performed to date, and remained so until December 21, 2001. Because WSS was unlicensed during some period
in which it performed work under the contract, it is barred from maintaining this action if any of the
work it did required licensure, or unless it can bring itself within the statutory exception for substantial
compliance, an issue to which we shall return.
First,
we address WSS's contentions that licensure was not required for any of the work it did before December 21,
2001. WSS is mistaken.
(i)
WSS may not segregate "acts" performed in furtherance of the contract.
First,
WSS insists it is entitled to recovery because the discrete tasks of ordering anchor bolts and preparing shop
drawings do not constitute performance and can be segregated from the subcontract.
A
strikingly similar attempt by an unlicensed contractor to segregate certain tasks from an integrated contract to
avoid the bar of section 7031 was rejected in Banis Restaurant Design, Inc. v. Serrano (2005)
134 Cal.App.4th 1035 (Banis).
In Banis, an unlicensed entity sought to recover for "design services" for a restaurant and market
construction project that included preparing electrical and plumbing drawings and specifications, coordination with
architects and engineers, and procurement of equipment and materials. (Id. at p. 1040.) In an attempt to
avoid section 7031, the plaintiff argued it had not acted as a contractor in providing design services or,
alternatively, that the contract could be segregated into discrete tasks. (Banis, supra, 134 Cal.App.4th at
p. 1046.) The court rejected plaintiff's attempt to parse the contract and concluded the services and materials
plaintiff provided were fixtures intended to be and actually physically incorporated into the project. (Id.
at pp. 1045-1047.) In language equally applicable here, the court stated the design plans reflected "coordination
of the [162 Cal.App.4th 592] architect . . . and . . . engineers. Through its own efforts and those of
others, plaintiff thereby undertook to 'construct,' 'alter,' 'add to,' 'subtract from,' and/or 'improve'
defendant's project. (See
� 7026.)
In short plaintiff was a contractor, and section 7031 bars plaintiff's suit for compensation." (Banis,
supra, 134 Cal.App.4th at p. 1044.) The court rejected plaintiff's attempt to parse the contract into discrete
tasks, only some of which required licensure. The contract was not severable because "each aspect of plaintiff's
work was integral to the restaurant project, and was not minor or incidental," but "part of an integral whole."
(Id. at p. 1047.) The same reasoning applies here. As Ramirez himself acknowledged at trial, the shop
drawings he prepared while WSS remained unlicensed were tasks for which the corporation bid and which were
performed in furtherance of the scope of the work included in the subcontract. Those tasks cannot be severed from
the parties' integrated agreement to avoid section 7031's bar to recovery.
[7]
We also find no merit in WSS's assertion that the ordering of bolts and preparation of shop drawings for which
it had bid could not have been tasks done "in performance of" the subcontract because the subcontract did not
exist until it was executed by Great West in January 2002, by which time WSS was licensed. Section 7031 applies
not only to formal agreements, but governs "any act or contract for which a license is required." The
Legislature's inclusion of the word "acts" was intended to broaden the statute's reach. (MW Erectors,
supra, 36 Cal.4th at p. 427.) The statute applies whether or not a party is operating under an executed
contract when performing tasks that require licensure. "The CSLL does not require contractors to operate
exclusively by formal contract; it simply seeks to deter them from offering or performing unlicensed
services for pay. . . . [
�] .
. . [O]ne may not avoid the all-or-nothing bar against recovery for unlicensed services simply because there is no
formal contract. In other words, one may not recover compensation for . . . any 'act' requiring a license
unless duly licensed 'at all times during the performance of that act. [Citation.]" (Id. at pp.
427-428, italics added.)
(ii)
Licensure required to prepare drawings and order materials.
WSS
also argues, and the trial court agreed, the drafting of shop drawings and ordering of anchor bolts was not work
performed under the contract, but prefatory tasks for which the corporation was not required to be licensed. WSS
is mistaken.
[8]
WSS prepared shop drawings detailing the steel work it intended to perform on the project and specifying "how
[it was] going to build the canopies," and submitted those drawings to the project architects and engineers for
approval. A contractor includes one who, like WSS, "offers to [162 Cal.App.4th 593] undertake . . . or
purports to have the capacity . . . or submits a bid" to do specific acts defined by statute as work engaged in
by a contractor, including the construction, alteration or repair of any part of any building, structure or
project. (
� 7026.)
Shop plans constitute such an offer or bid. Through them WSS purported to possess the capacity to undertake the
steel work and construction it proposed to perform on the project within the meaning of section 7026, and thus was
acting as a contractor. WSS was required to possess a contractor's license when it submitted its shop plans
specifying the scope of the structural steel construction it intended to perform on a public works project.
(See
�� 6737.3
[exempting licensed contractors from requirements applicable to civil engineers for, among other things,
designing structures for work the contractor is to perform and supervise, in accordance with construction industry
standards and codes and within his or her license classification, and for the preparation of shop or field
drawings for work he or she has contracted to perform], and 6731 [defining scope of civil engineering].) The
public has a right to expect the party designing such plans -- the improper implementation of which could have
serious consequences at a school for deaf children -- will, at a minimum, have the qualifications required and to
possess a valid contractor's license.
[9]
The same logic negates WSS's assertion it was not required to be licensed to order materials meant to be
incorporated in the ultimate construction, or because it did not perform the steel galvanization itself, but
coordinated and oversaw that process which was actually performed by a third party vendor. "Section 7026 plainly
states that both the person who provides construction services himself and one who does so 'through others'
qualifies as a 'contractor.' The California courts have also long held that those who enter into construction
contracts must be licensed, even when they themselves do not do the actual work under the contract. [Citations.]
Indeed, if this were not the rule, the requirement that general contractors be licensed would be completely
superfluous." (Vallejo Development Co. v. Beck Development Co. (1994)
24 Cal.App.4th 929,
941.) The reason contractors must be licensed even if they hire subcontractors to do the actual work is so that the
public is protected ' "against persons who are unqualified to perform the required work.' " (Currie v.
Stolwitz (1959)
169 Cal.App.2d 810,
814-815.) The same reasoning governs the services subcontractor WSS provided in ordering and overseeing the
preparation of materials ultimately intended to be incorporated in the project, i.e., to become "part of an
integral whole." (Banis, supra, 134 Cal.App.4th at p. 1047.)
Because
WSS was unlicensed during a period in which it performed work under the contract for which a contractor's
license is required, it is barred from any recovery unless it can bring itself within the statutory exception
for substantial compliance, an issue to which we now turn. [162 Cal.App.4th 594]
b.
WSS has not made a sufficient showing of substantial compliance; it was not licensed before December 21,
2001, and may not rely on the license history of another individual or entity.
WSS
contends it substantially complied with the licensing requirements because, as the corporation's RMO, Ramirez
previously qualified a WSS partnership for a contractor's license and held various individual contractor
licenses of his own at all times before and after the corporation obtained its license.
fn. 8 WSS has not made a sufficient showing of substantial compliance. The contract at issue was
between Great West and WSS, the corporation, the entity which bid the project and the only entity to have performed
work for which recovery was sought in this action, not WSS, the partnership or Ramirez as an individual. WSS was
incorporated for almost two years before it applied for a contractor's license in August 2001. Unequivocal evidence
at trial showed the sole license held by the corporation "was issued 12/21/2001 and did not exist before that
date." The WSS partnership license was not -- and could not have been -- transferred or reissued to WSS, the
corporation. (See
� 7075.1,
subd. (a) ["No license . . . shall be transferable to any other person or entity under any circumstances].)
fn.
9 The licensing history of the partnership and Ramirez are not relevant to the WSS corporate
license history.
Nor
is the fact that Ramirez was the qualifier for the partnership, an unrelated entity, relevant to the
corporation's license history. WSS's reliance on Asdourian v. Araj (1985)
38 Cal.3d 276 (Asdourian),
is misplaced. Asdourian no longer states the law. [162 Cal.App.4th 595]
In
Asdourian, a contractor failed to obtain a license in his own name. He had planned to conduct business as
a sole proprietor under a fictitious name, and obtained a license in that name. Because he lacked a license, the
plaintiff was out of compliance with the law. If strict compliance with section 7031 was required, he could not
maintain an action for damages. Applying the judicial doctrine of substantial compliance, and noting that, as
here, the purposes of the CSLL were satisfied (the contractor was qualified for licensure and supervised the
work), the court concluded the defendant "should not be able to avoid his obligation to compensate plaintiff for
the work he performed." (Asdourian, supra, 38 Cal.3d at p. 285.)
The
court traced the judicial doctrine of substantial compliance back to its earlier decisions, Gatti v. Highland
Park Builders, Inc. (1946)
27 Cal.2d 687 (Gatti)
and Latipac, Inc. v. Superior Court (1966)
64 Cal.2d 278 (Latipac),
on which WSS also relies. The court noted that, " '[f]or nearly three decades [it had] developed and applied to
cases arising under section 7031 the doctrine of "substantial compliance;" during that entire period the
Legislature [had] indicated no hint of disapproval of this construction.' " (Asdourian, supra, 38 Cal.3d at
p. 287, quoting Latipac, supra, at p. 281.) Indeed, by the time Asdourian was decided that time had
been extended another 19 years, and the statute had even been amended in 1961 to make the exception recognized in
Gatti explicit. (Stats. 1961, ch. 1325,
� 1,
p. 3015; see Asdourian, supra, 38 Cal.3d at p. 284, fn. 6.)
However,
Asdourian, Gatti, and Latipac are no longer the law. In 1989, the Legislature added
subdivision (d) [now subdivision (e)] to section 7031 expressly repudiating the judicial doctrine of substantial
compliance. That subdivision provides "The judicial doctrine of substantial compliance shall not apply under
this section where the person who engaged in the business or acted in the capacity of a contractor has never
been a duly licensed contractor in this state." "Person" is broadly defined to include corporations.
(
� 7025.)
The sole exception to the subdivision permits a court to find substantial compliance with the statutory
requirements if the person whose licensure is challenged can show it was properly licensed as a state contractor
sometime before performance of the act or contract, reasonably and in good faith attempted to maintain licensure,
and did not know or reasonably should not have known it was no longer licensed. (
� 7031,
subd. (e).) The intent and effect of this legislative change was to severely limit the doctrine of substantial
compliance; it only applies if all three elements of subdivision (e) are satisfied. (Construction
Financial, supra, 53 Cal.App.4th at p. 180.) [162 Cal.App.4th 596]
[10]
WSS, the corporate entity or "person" engaged in the business and which acted in the capacity of contractor,
does not and cannot argue it was ever licensed as a contractor or held that status at a time that
preceded its performance in this case. The substantial compliance doctrine is unavailable to a contractor who
has not been duly licensed at some point before beginning performance of the contract. (MW Erectors,
supra, 36 Cal.4th at p. 419; see also General Ins. Co. v. Superior Court (1972)
26 Cal.App.3d 176,
184 [precluding unlicensed corporation from recovery even though its sole shareholder was at all times licensed
because, to find substantial compliance under the circumstances "would emasculate the statutory language and
nullify [section 7031's] purpose . . . ."]; see also Opp v. St. Paul Fire & Marine Ins. Co.
(2007)
154 Cal.App.4th 71, 79
[unlicensed corporate contractor may not enforce contract on the basis of an individual employee's license].) There
is no legitimate basis for applying the doctrine of substantial compliance.
[11]
We are cognizant of the harshness of this result. But the law is clear. If the bar of section 7031 applies, it
applies regardless of equitable considerations. As discussed above, the Supreme Court has determined the statute
"represents a legislative determination that the importance of deterring unlicensed persons from engaging in the
contracting business outweighs any harshness between the parties, and that . . . such deterrence can best
be realized by denying violators the right to maintain any action for compensation in the courts of this state.
[Citation.] . . .' [Citations.]" (Hydrotech, supra, 52 Cal.3d at p. 995.) We are bound by this reasoning.
(Auto Equity Sales, Inc. v. Superior Court (1962)
57 Cal.2d 450,
455.) WSS was never licensed before it commenced work under the subcontract. That lack of prior licensure precludes
application of the statutory substantial compliance exception. Thus, irrespective of Ramirez's good faith,
competence and his or the WSS partnership's prior license history, section 7031 bars the corporation from
maintaining this action. The trial court erred in denying nonsuit.
3.
Remaining issues not reached.
In
view of the discussion above, it is unnecessary to address whether WSS acted in good faith, whether the court
erred in permitting WSS's expert to testify as to certain matters, whether the damages award was excessive, or
any other issues. [162 Cal.App.4th 597]
DISPOSITION
The
judgment is reversed. The matter is remanded with instructions to the trial court to vacate the judgment and
enter judgment in favor of Great West and Fidelity. Great West and Fidelity shall recover their costs in this
proceeding. (Cal. Rules of Court, rule 8.276(a)(1) & (2).)
Rubin,
J., and Flier, J., concurred.
�
FN 1. Our
factual recitation and discussion are limited to the dispositive issue of licensure.
�
FN 2. The
interests of Great West and Fidelity are aligned on appeal. Thus, for the sake of brevity, we will refer to
appellants collectively as Great West.
�
FN 3. Initially,
this litigation involved Great West and its sureties on four separate construction projects. Settlements were
reached as to all projects except the Middle School for the Deaf.
�
FN 4. A
portion of Great West's motion to vacate the judgment was granted on grounds not relevant here.
�
FN 5. We
decline WSS's invitation to ignore the licensure argument because the issue was not raised until the middle of
trial. As required by statute, the issue was fully vetted at a special evidentiary hearing. Moreover, the defense
of illegality under section 7031 may be raised any time, even as late as on appeal. (Lewis & Queen,
supra, "48 Cal.2d at pp. 148-149.)
�
FN 6. In
its bid, WSS proposed perform the following services:
"1.
Fabricate and Install Canopies 1, 2, 3, 4, 5, 6, 7;
"2.
Qty. 7 Canopies to be Galvanized;
"3.
Anchor Bolts with Templates F.O.B.;
"4.
4x4x3/16 T.S. Columns with Grey Primer;
"5.
Qty. 3 Roof Access Ladders;
"6.
4"x6"x15 lbs per ft. Galv. Chain;
"7.
Shop Drawings."
�
FN 7. Great
West argues convincingly that it was not possible for all the work WSS invoiced on December 25, 2001, to have been
done between the date WSS received its license and year end. That is because, according to Ramirez, it can take
five days to several weeks to galvanize steel, depending on the time of year. Galvanization and fabrication of
steel are independent processes. WSS does not do the galvanization; it hires a third party vendor to perform that
process, which must be done before WSS can fabricate the steel. WSS was closed for business on December 25, 2001.
There were only four business days between the time the license was issued on December 21 and December 31, 2001,
during which time WSS claimed it purchased these materials and had them galvanized. Great West asserts that, if WSS
actually waited until its license issued to order and have the steel galvanized, there was insufficient time for it
to have completed the work invoiced on December 25, and logic dictates some tasks invoiced that date were performed
prior to licensure. WSS insists the tasks for which Great West was billed on December 25 were performed after it
received its license. This dispute is immaterial; if WSS was not licensed at all relevant times, it may not recover
for any work it performed under the contract if the work required licensure, unless it can avail itself of the
statutory substantial compliance exception. Leaving the third invoice aside, there is no dispute WSS performed work
(prepared shop drawings and ordered materials) prior to December 21, 2001. The only question is whether a license
was required to perform those tasks.
�
FN 8. Ramirez
was the qualifier for licenses issued to a WSS Partnership and its predecessor partnership, RAM Welding. When WSS,
the corporation, was formed in 1999, Ramirez was informed by the Board he was not eligible to qualify for a license
for the corporation without first disassociating from WSS partnership, which he did. Ramirez also held valid
individual licenses. Ramirez's individual licenses and the WSS partnership's license were in effect when the
corporation bid the project in August 2001. Ramirez submitted a notice of disassociation to the Board in
mid-November 2001, with an effective date of December 1, 2001. WSS contends it acted in good faith and
substantially complied with section 7031, because it believed the corporation's license would be issued
contemporaneously with cancellation of the partnership's license. In any event, WSS insists there was only a short
"gap" in licensure between the time Ramirez disassociated from the partnership as a condition of the issuance of
WSS' corporate license. Compelling as these facts may be, they do not satisfy the rigid statutory requirements for
substantial compliance. There was no "gap" in licensure. WSS Industrial Construction, Inc., was never licensed
before December 21, 2001. It is irrelevant that WSS, a partnership and unrelated entity, once held a license, that
Ramirez was the qualifier for both the partnership and the corporation, or that Ramirez held valid individual
licenses at all times.
�
FN 9. A
license number may be reissued or reassigned to a corporation under limited circumstances, none of which obtain
here. (See
� 7075.1,
subds. (1), (3) & (4).)
|