Greenbriar
Homes Communities, Inc. v. Superior Court (Couris) (2004)117 Cal.App.4th 337, -- Cal.Rptr.3d --
[No.
C044210. Third Dist. Mar. 8, 2004.]
[As
modified Mar. 9, 2004.]
GREENBRIAR
HOMES COMMUNITIES, INC., Petitioner, v. SUPERIOR COURT OF SAN JOAQUIN COUNTY, Respondent; ALBERT COURIS et al.,
Real Parties in Interest.
(Superior
Court of San Joaquin County, No. CV018524, K. Peter Saiers, Judge.)
(Opinion
by Nicholson, J., with Scotland, P. J., and Davis, J., concurring.)
COUNSEL
Cox,
Castle & Nicholson, Robert D. Infelise and Alicia N. Vaz for Petitioner.
John
P. Dwyer for California Building Industry and Association of Home Builders Association of Northern California as
Amicus Curiae on behalf of Petitioner.
June
Babiracki Barlow and Neil D. Kalin for California Association of Realtors as Amicus Curiae on behalf of
Petitioner.
No
appearance for Respondent.
Verboon,
Milstein & Peter, Fred M. Adelman, Lee Jackson; Esner & Chang and Stuart B. Esner for Real Parties in
Interest. [117 Cal.App.4th 340]
OPINION
NICHOLSON,
J.-
By
this action, petitioner challenges the trial court's denial of its motion to compel reference to a referee in
the underlying action. It argues the trial court abused its discretion (1) by not determining the contractual
reference provision on which petitioner relied is enforceable and not unconscionable, and (2) by denying the
motion based on the alleged potential of a multiplicity of suits. We grant the petition in part.
BACKGROUND
Petitioner's
predecessor in interest constructed single-family homes in a Stockton development commonly known as Chantelane.
fn.
1 Real parties in interest are owners of Chantelane homes. fn.
2 They brought individual actions [117 Cal.App.4th 341] against petitioner to recover
for damages allegedly suffered due to defective construction of their homes. The trial court consolidated their
actions into the matter of Acosta v. Greenbriar Homes Communities, Inc., San Joaquin Superior Court case
No. CV018524, consolidated with case No. CV019335 and case No. CV020674.
Real
parties' first amended complaint alleged 69 different homes were involved in the action. Of those, 43 were owned
by real parties who purchased their homes from petitioner and were in privity of contract with petitioner
(original purchasers). The remaining 26 were owned by real parties who were not the original purchasers and were
not in privity of contract with petitioner (nonoriginal purchasers).
The
purchase and sale agreements between petitioner and the original purchasers required all disputes arising out of
the agreement to be determined by a judicial referee pursuant to Code of Civil Procedure sections 638-645.1. The
parties agreed the referee was to decide all issues of fact and law and to issue a final judgment. The parties
were to bear the costs of the judicial reference equally.
Pursuant
to the reference agreement, petitioner filed a motion to compel the court to order the consolidated action be
heard by a referee. At the same time, petitioner demurred to the first amended complaint and filed a motion to
strike class action allegations.
Real
parties opposed the motion to compel, arguing the agreement to decide all disputes by reference was
unconscionable. They also claimed enforcing the reference provision would result in the original purchasers
litigating in the reference proceedings while at the same time the non-original purchasers would be litigating
in the trial court.
The
trial court heard the motions on March 19, 2003. It granted the demurrer with leave to amend and granted the
motion to strike, but it took the motion to compel under submission.
By
ruling dated April 8, 2003, the trial court denied the motion to compel judicial reference. Its order stated
simply, the motion "is hereby denied as it [117 Cal.App.4th 342] would cause multiplicity of lawsuits."
The order said nothing on the issue of the reference provision being unconscionable.
Petitioner
filed a motion for reconsideration. Petitioner argued new judicial authority required a different decision.
Also, petitioner included with its motion, as supporting evidence, copies of contracts between it and its
Chantelane subcontractors. The subcontractors had agreed that in a dispute between petitioner and third parties
that resulted in petitioner making a claim against a subcontractor, petitioner could elect to bring the
subcontractor into the forum that would determine the dispute between petitioner and the third party. Petitioner
argued these provisions would prevent the problem of multiplicity feared by the trial court as any of real
parties' claims against subcontractors would, at petitioner's election, have to be resolved in the reference
proceeding.
Meanwhile,
real parties filed their second amended complaint and named 45 subcontractors as Doe defendants. They also
opposed the motion for reconsideration, claiming petitioner had failed to offer any new facts, law or
circumstances warranting the motion.
The
court commenced the hearing on petitioner's reconsideration motion by stating: "The Court denied the initial
request for the stayed proceedings because it only applied to a few of the parties and not to all the parties.
And I thought they would be duplicate litigation of the case if one was in the arbitration [sic] system
and the other was in the court system."
By
ruling dated June 5, 2003, the trial court denied petitioner's motion for reconsideration. It offered no
explanation of its order.
Petitioner
filed a demurrer to the second amended complaint. It also filed a writ petition in this court for relief from
the trial court's denial of its motion to compel. We issued an alternative writ of mandate. We also stayed all
further proceedings in the underlying action.
DISCUSSION
A
reference for private judging is called a general reference. The referee is empowered to "hear and determine any
or all of the issues in an action or proceeding, whether of fact or of law" (Code Civ. Proc., § 638, subd. (a)),
and to make a binding decision that "must stand as the decision of the court." (Code Civ. Proc., § 644, subd.
(a).)
An
order of general reference must be based on either the agreement of the parties filed with the clerk or judge or
entered in the minutes or in the docket, [117 Cal.App.4th 343] or the motion of a party seeking to
enforce a written contract or lease that requires any controversy arising from it to be heard by a referee.
(Code Civ. Proc., § 638.)
[1]
A predispute agreement for appointment of a referee is enforceable only if part of a "written contract or
lease." (Code Civ. Proc., § 638.) The existence of such an agreement is determined under standard rules of
contract interpretation. (See Sy First Family Ltd. Partnership v. Cheung (1999)
70 Cal.App.4th 1334,
1341 [83 Cal. Rptr. 2d 340]; Badie v. Bank of America (1998)
67 Cal.App.4th 779,
800-804 [79 Cal. Rptr. 2d 273].)
[2]
The parties' consent is essential for a general reference. (In re Edgar M. (1975)
14 Cal.3d 727,
734 [122 Cal. Rptr. 574, 537 P.2d 406]; Murphy v. Padilla (1996)
42 Cal.App.4th 707,
714 [49 Cal. Rptr. 2d 722].) Absent consent, an order of general reference would be an unconstitutional "abdication
of judicial responsibility." (Aetna Life Ins. Co. v. Superior Court (1986) 182 Cal. App. 3d 431, 436 [227
Cal. Rptr. 460].)
On
this just-discussed point, we concur in the trial court's ruling to the extent it denied petitioner's motion to
compel with regards to the nonoriginal purchasers. Having never consented to judicial reference, they cannot now
be forced to participate in a general reference by the court.
With
the above principles in mind, we now turn to petitioner's remaining arguments as they apply to the original
purchasers who agreed to judicial reference.
I
Unconscionability
The
trial court made no determination regarding whether the reference provision in the sale contract was
unconscionable. However, unconscionability was the real parties' main argument against the motion to compel.
Because the issue is solely one of law (Pardee Construction Co. v. Superior Court (2002)
100 Cal.App.4th 1081,
1088 [123 Cal. Rptr. 2d 288] (Pardee Construction)), is potentially dispositive, and because the parties'
arguments on the issue are fully contained in the record, we address the issue here. We conclude the reference
provision is not unconscionable.
"Although
the 'doctrine of unconscionability' was judicially created [citation], Civil Code section 1670.5 now provides a
statutory basis for refusing to enforce a contract which the court finds 'as a matter of law ... to have been
[117 Cal.App.4th 344] unconscionable at the time it was made. ...' The crucial term, 'unconscionable,' is
not defined, but the law has clearly established that the term has both a procedural and a substantive element.
The [procedural element] takes into consideration the parties' relative bargaining strength and the extent to
which a provision is 'hidden' or unexpected, while the substantive element requires terms that 'shock the
conscience' or at the least may be described as 'harsh or oppressive.' [Citation.] Both elements must be
present, but 'the more substantively oppressive the contract term, the less evidence of procedural
unconscionability is required to come to the conclusion that the term is unenforceable, and vice versa.'
[Citation.]" (Woodside Homes of Cal., Inc. v. Superior Court (2003)
107 Cal.App.4th 723,
727 [132 Cal. Rptr. 2d 35] (Woodside Homes).)
The
reference provision at issue here appeared in standardized sale agreements used with each original purchaser.
The provision, paragraph 16(f) of the sale agreement, appears in the same font and font size as most of the
agreement's sections, and appears at the end of the agreement immediately above the signature block for the
purchaser. The provision reads in full:
"(f)
Judicial Reference
"(1)
It is the desire and intention of the parties to agree upon a mechanism and procedure under which any
controversy, breach or dispute arising out of this Agreement, will be resolved in a prompt and expeditious
manner. Accordingly, except as otherwise provided in Paragraph 11 above [concerning arbitration of disputes over
the use of deposit moneys as liquidated damages], any controversy, breach or dispute arising out of this
Agreement, or relating to the interpretation of any term or provision of this Agreement, shall be heard by a
reference pursuant to the provision of the California Code of Civil Procedure, Sections 638-645.1 inclusive;
"(2)
The parties shall promptly and diligently cooperate with one another and the referee, and shall perform such
acts as may be necessary to obtain prompt and expeditious resolution of the dispute or controversy in accordance
with the terms hereof;
"(3)
The Parties agree that the referee shall have the power to decide all issues of fact and law and report his/her
decision hereon, and to issue all legal and equitable relief appropriate under the circumstances before him/her;
"(4)
The parties shall agree upon a single referee who shall then try all issues, whether of fact or law, and report
a finding and judgment thereon. If the parties are unable to agree upon a referee within ten (10) days of a
written request to do so by any party, then any party may thereafter seek to have a referee appointed pursuant
to the California Code of Civil Procedure Sections 638 and 640 ; [117 Cal.App.4th 345]
"(5)
The cost of such a proceeding shall be borne equally by the parties to the dispute."
The
provision is not procedurally unconscionable. There is no evidence the original parties had no meaningful choice
not to agree to the reference, or that any of them attempted to negotiate this provision and were rebuffed.
There also is no element of surprise in the provision. The provision is written clearly in the same sized font
as the rest of the agreement, and is easily understood. The provision was not buried in the agreement, but in
fact appeared at a location where the purchaser was almost certain to see it--immediately above where the
purchaser would sign the agreement.
The
provision is also not substantively unconscionable. Its terms are not so one-sided as to "shock the conscience,"
nor are they harsh or oppressive. It did not limit the amount or type of relief the original purchasers could
obtain. By means of judicial reference, the provision attempted to ensure the parties would have their rights
enforced and arguments resolved in as efficient and fair a manner available to them, consistent with the rules
of procedure and evidence that apply to a trial. Even the referee' s fees were to be shared equally.
At
trial, real parties argued the provision was unconscionable because it required them to shoulder half of the
costs. They cited Ting v. AT&T (9th Cir. 2003) 319 F.3d 1126, 1151, where the federal court
determined an arbitration agreement requiring customers to split the arbitrator's fees was categorically
unreasonable because it imposed on consumers costs greater than they would bear if they filed the same complaint
in court. Ting is distinguishable. The California Supreme Court has applied this categorical rule in the
context of employment arbitration where the employee relies on an unwaivable statutory right (see Armendariz
v. Foundation Health Psychcare Services, Inc. (2000)
24 Cal.4th 83,
110-111 [99 Cal. Rptr. 2d 745, 6 P.3d 669]), but it has specifically not determined the rule applies in consumer
arbitrations. (Cruz v. PacifiCare Health Systems, Inc. (2003)
30 Cal.4th 303,
317, fn. 3 [133 Cal. Rptr. 2d 58, 66 P.3d 1157].)
One
appellate court has determined the Ting/Armendariz rule does not apply in consumer arbitrations, in part
because governing legislation reflects the Legislature's intent not to impose such a categorical rule.
(Gutierrez v. Autowest, Inc. (2003)
114 Cal.App.4th 77, 97
[7 Cal. Rptr. 3d 267].) Instead, "[t]he determination that arbitral fees in consumer cases are unreasonable should
be made on a case-by-case basis, with the consumer carrying the burden of proof." (Ibid.)
[3]
Statutes governing judicial references require the referee's fees be paid "as agreed by the parties." (Code Civ.
Proc., § 645.1, subd. (a).) Here, [117 Cal.App.4th 346] where the parties have agreed on payment of the
reference costs in a consumer claim brought on contract and tort causes of action, we conclude the categorical
rule espoused by the Ting court does not apply.
During
oral argument and in response to our questioning, real parties asserted the risk of multiple actions proceeding
in different forums was such as to render the agreements effectively unconscionable. However, real parties
admitted no reported case supported this position. Moreover, any risk from multiple actions was significantly
minimized by the petitioner contractually binding all of its subcontractors to join in actions against it no
matter the forum. As a result, the trial court has the means both to enforce the valid reference provisions and
to ensure a plaintiff's rights are not litigated concurrently in different forums.
[4]
Under these circumstances, we conclude the reference provision was not unconscionable. (Cf. Pardee
Construction, supra, 100 Cal.App.4th 1081, 1089-1090, where the Court of Appeal determined a judicial
reference clause in a real estate purchase contract was unconscionable in part because the provision was "buried
in the form contracts," "physically difficult to read," suffered from a possibly misleading caption, was silent
on referee fees, and prohibited the recovery of punitive damages.)
II
Denial
Based on Multiplicity of Lawsuits
[5]
Having determined the reference provision was not unconscionable, we must decide whether the trial court abused
its discretion in not enforcing the provision against the original purchasers based on the possibility of
multiple lawsuits. We conclude it did.
Because
the provision was not unconscionable or otherwise invalid, petitioner claims the court had to enforce the
provision. The court, petitioner argues, had no authority to ignore the valid agreement between the parties on
the basis of multiplicity of actions.
Real
parties, however, argue the court had discretion not to enforce the reference provision against the original
purchasers. That discretion, they claim, is derived from analogous statutory authority given courts under Code
of Civil Procedure section 1281.2 to refuse to enforce arbitration agreements pending a court action
between a party to the arbitration agreement and a third party.
The
statute requires a court to enforce an arbitration agreement unless the court determines, among other
possibilities, a "party to the arbitration agreement is also a party to a pending court action or special
proceeding with a [117 Cal.App.4th 347] third party, arising out of the same transaction or series of
related transactions and there is a possibility of conflicting rulings on a common issue of law or fact. For
purposes of this section, a pending court action or special proceeding includes an action or proceeding
initiated by the party refusing to arbitrate after the petition to compel arbitration has been filed, but on or
before the date of the hearing on the petition. [¶] ... [¶]
"If
the court determines that a party to the arbitration is also a party to litigation in a pending court action or
special proceeding with a third party ... the court (1) may refuse to enforce the arbitration
agreement and may order intervention or joinder of all parties in a single action or special proceeding; (2)
may order intervention or joinder as to all or only certain issues; (3) may order arbitration among the parties
who have agreed to arbitration and stay the pending court action or special proceeding pending the outcome of
the arbitration proceeding; or (4) may stay arbitration pending the outcome of the court action or special
proceeding." (Code Civ. Proc., § 1281.2, subd. (c), italics added.)
[6]
Code of Civil Procedure section 1281.2 is a specific statute that creates a special rule, which invalidates
only arbitration agreements. Were it not for this statute, a court could refuse to enforce an arbitration
agreement only upon such grounds as exist at law or in equity to invalidate any other contract. (Armendariz
v. Foundation Health Psychcare Services, Inc., supra, 24 Cal.4th at p. 98.)
Real
parties acknowledge Code of Civil Procedure section 1281.2 does not expressly apply to judicial references, but,
relying on Pardee Construction and Woodside Homes, assert sufficient similarity between
arbitration agreements and reference agreements allows the statute to authorize the trial court's ruling. Both
of those cases concerned the enforceability of judicial reference provisions similar to the one before us. The
Pardee Construction court ruled its provision was unconscionable; the Woodside Homes court ruled
its provision was not unconscionable. The Court of Appeal, Fourth Appellate District, decided both cases.
In
both, the courts commented the review of arbitration statutes was "informative" (Pardee Construction,
supra, 100 Cal.App.4th at p. 1093) and "justified" (Woodside Homes, supra, 107 Cal.App.4th at p. 727)
when determining whether a reference provision was unconscionable. However, neither court stated the arbitration
statutes created grounds outside of those existing at law or equity by which a court could invalidate reference
agreements determined not to be unconscionable. Indeed, the Woodside Homes court specifically noted Code
of Civil Procedure section 1298.7, another statutory exception to enforcing certain arbitration agreements,
applied only to arbitration agreements and not to judicial reference agreements. [117 Cal.App.4th
348] (Woodside Homes, supra, at p. 726, fn. 2.) Significantly, by concluding the reference agreements
were not unconscionable, the Woodside Homes court determined the agreements were enforceable.
(Id. at pp. 725, 736.)
At
oral argument, real parties asserted if a court could not invalidate a judicial reference agreement due to
multiplicity of actions, a ground on which Code of Civil Procedure section 1281.2 allows a court to invalidate
an arbitration agreement, then by extension a court could also not invalidate a judicial reference agreement on
the other grounds Code of Civil Procedure section 1281.2 provides for invalidating arbitration agreements,
namely the right to compel arbitration has been waived or grounds exist for the revocation of the arbitration
agreement. We disagree.
[7]
A general reference such as the one sought by petitioner may occur only upon the agreement of the parties. If
one party has waived the right to compel or the agreement is subject to revocation, no such agreement exists.
Code of Civil Procedure section 1281.2 does not provide courts with any additional authority they do not already
have to refuse to enforce a waived or revoked term of agreement. Real parties cite us to no case holding the
potential for multiple actions invalidates the parties' agreement to have all disputes decided by judicial
reference.
Had
the Legislature intended to allow judicial reference agreements to be invalidated on the basis of other pending
or multiple actions, it could have adopted a statute so stating. Without such statutory authorization, however,
both the trial court and we lack authority to invalidate an otherwise valid contractual agreement. "[W]e do not
rewrite any provision of any contract [or any statute] ... for any purpose." (Certain Underwriters at Lloyd's
of London v. Superior Court (2001)
24 Cal.4th 945,
968 [103 Cal. Rptr. 2d 672, 16 P.3d 94].)
DISPOSITION
The
petition for writ of mandate against the trial court's order denying petitioner's motion to compel judicial
reference of those claims brought by nonoriginal purchasers is denied. As to those claims brought by original
purchasers, the petition is granted. The clerk of this court is ordered to serve a peremptory writ of mandate
directing the respondent court to set aside and vacate its ruling of April 8, 2003, denying petitioner's motion
to compel to the extent that order concerned claims brought by original purchasers. [117 Cal.App.4th 349]
Our
stay of the underlying action is vacated upon finality of this opinion. The parties shall bear their own costs.
Scotland,
P. J., and Davis, J., concurred.
On
March 30, 2004, the opinion was modified to read as printed above.
FN 1. For
convenience, we refer to petitioner, Greenbriar Homes Communities, Inc., and its predecessors in interest,
Greenbriar Homes Communities, LLC, and Greenbriar Blairmore Partners, L.P., collectively as petitioner.
FN 2. Petitioner
named the following as real parties in interest: Albert & Kabline Couris, Albert & Teresa Garcia, Ami M.
Dang, Andy & Shelly Nikitin, Angelina Novelozo, Ann M. Reid, Anthony F. & Belinda M. Costa, Arthur W. II
& Lora E. Sandman, Azlena Lang, Barbara Silver & Jeannie Swanson, Bonifacio L. & Nolita Luna, Brian
& Deborah Bartolomei, Carl & Tracy Mata, Carol J. Migliore, Carol Louise Cruz, Craig M. & Diane L.
Crumpacker, Daniel L. & Judy K. Segraves, Danilo T. & Elsa N. Ursolum, Dannie & Barbara Odle, David A.
& Raycine M. Sommers, David J. & Tammy S. Dodd, David W. Jr. & Michelle Coveney, Dominick & Andrene
T. Mazzanti, Donald E. & Barbara Snell, Doug & Angela Titus, Duane & June Madden, Eddie Gene &
Heather Wunsch, Eric & Karen Duran, Errol J. Sr. & Juanita F. Coustaut, Eugene Nord & Mary M. Thompson,
Fred & Kathy M. Acosta, Gerd U. & Pamela Kerr Pretzel, Gordon K. C. & Colleen A. Lee, Jack Lee &
Linda Marie Elphick, James Mandich & Carolyn Bishop, James W. & Leslie Andersen, Jannamarie E. Hines,
Jean-Loree Armanino, Jennifer Hawkins, Jerry C. Jr. & Kristy D. Johnston, John Albert & Mary Abou-Elias,
John & Michele Lease, John & Mindy Birkett, John & Rachael Jaramillo, John B. & Donna W. Yim, John
Jr. & Virginia F. Geigle, John M. & Michelle R. Gabbard, John R. & Virginia L. Stevenson, Johnny H. Jr.
& Debra L. Griffin, Johnny K. & Bonnie S. Lew, Jose T. & Gwen Aguero, Joseph N. & Maria
Wasielewski, Judith A. McOwen, Justin & Barb Wilson, Kathleen D. & Rodney E. Van Nostern, Kathy Gardner
& Karen Laack, Kenneth & Diane Knutson, Kevin & Nanette Fisher, Larry Lee & Margaret Ann Johnson,
Lawrence & Gladys Grayson, Lawrence & Katherine Crumbly, Lester T. Iseri, Lloyd M. & Paulina E. Vestal,
Luther & Nuiko Shimozaki, Lyndon & Theresa Tumakay, Maribel & Noel Jumaoas, Mark P. & Jane E.
Thrift, Mark W. & Cathleen J. Conn, Matthew & Kimberly Merseth, Maurice L. Jr. & Marcia Benson, Michael
S. & Janet M. Carey, Michael S. & Ramona L. Singer, Miguel DeToro & Susan L. Sherman, Mike &
Cynthia Relloque, Milford L. Mullins, Nick Nguyen, Patricia D. Daniels, Paul & Marion Sachs, Philip & Lisa
Debeaubien, Richard & Gayle L. Bastear, Richard Jon & Tamara L. Mecham, Robert & Robin Ceniceros,
Robert Huynh & Tram T. Nguyen, Roland G. Corpus, Roqueta Harvey, Salvador & Kimberly K. Juarez, Salvador F.
& Utona L. Guillen, Scott Alan & Laura Jean Berger, Shannon & Diane E. Martin, Stacy A. & Lisa A.
Marks, Stephen K. & Julie K. Olson, Stephen P. Orlando, Tawfik & Fadia Zammar, Terry L. & Lisa M.
Pruitt, Terry W. & Kristie D. Toler, Vernon M. & Lenore F. Uyeda, W. C. Logan, Wilfred K. F. Lee, William
A. & Mary K. Kelley, William B. & Susan P. Belisario, and William M. & Meg A.
Sorrells.
|