Jackson
Plaza Homeowners Assn. v. Alcal Roofing and Insulation (2002), Cal.App.4th
[No.
A091787. First Dist., Div. Four. Apr. 30, 2002.]
JACKSON
PLAZA HOMEOWNERS ASSOCIATION, Plaintiff and Appellant, v. ALCAL ROOFING AND INSULATION Cross-defendant and
Respondent. [And five other cases. fn.
* ]
[Opinion
certified for partial publication. fn.
† ]
(Superior
Court of the City and County of San Francisco, No. 978926, Ronald E. Quidachay, Judge.)
(Opinion
by Rivera, J., with Kay, P. J., and Reardon, J., concurring.)
COUNSEL
Williams,
Wester, Hall & Nadler and Scott Williams for Appellant Jackson Plaza Homeowners Association.
Gordon
& Rees, S. Mitchell Kaplan and Kathleen A. Foley, for Appellant W. Wong Construction.
Chapman
& Intrieri, John W. Chapman and Kurt T. Hendershott for Respondent Alcal Roofing and Insulation.
Carroll,
Burdick & McDonough, Jack T. Friedman and Tara Narayanan, Lewis, D'Amato, Brisbois & Bisgaard and John
N. Carr, Valerian, Patterson, Field & McGraw and Christian Lucia for Respondent Atlas Heating and
Ventilating Co., Ltd.
Glaspy
& Glaspy and Brian S. O'Malley for Respondent New West Roofing, Inc.
Susan
H. Handelman for Respondent Gonzalez Roofing & Waterproofing Company.
OPINION
RIVERA,
J.-
In
this consolidated construction defects action, Jackson Plaza Homeowners Association (HOA) appeals from summary
judgments entered in favor of respondent W. Wong Construction and respondent subcontractors Alcal Roofing and
Insulation (Alcal), Atlas Heating and Ventilating Co., Ltd. (Atlas), New West Roofing, Inc. (New West) and
Gonzalez Roofing & Waterproofing Company (Gonzalez). HOA contends that the trial court erred in ruling that
the action was barred by the 10-year statute of limitations set forth in Code of Civil Procedure fn.
1 section 337.15 for actions to recover damages for latent construction defects. We conclude
that there is a triable issue of fact on whether the 10-year limitations period was subject to equitable tolling
for repairs undertaken by Wong Construction and Gonzalez after the notice of completion was recorded. We
therefore reverse the judgment in favor of Wong Construction on HOA's complaint and the judgment in favor of
Gonzalez on Wong Construction's cross-complaint.
I.
FACTUAL BACKGROUND
The
Jackson Plaza condominium project located at 1591 Jackson Street in San Francisco was completed in 1985. The
Madja Corporation was the developer of the project. Respondent Wong Construction was the general contractor of
the project. Respondents Alcal, Atlas, New West, and Gonzalez were subcontractors on the project. A notice of
completion of the project was recorded on October 26, 1985.
HOA
is a nonprofit corporation organized for the purpose of managing the project. fn.
2 In late 1985 and early 1986, HOA became aware of several problems at the project including
water leaks in the roof, the garage and the windows and sliding glass doors. Tai Associates/Architects (TAA),
the principal architect for the project, prepared punch lists of the repairs to be completed. In 1990, HOA filed
an action against respondents and others. However, HOA subsequently dismissed the action when it determined that
the problems could be remedied at minimal cost.
In
1995, HOA discovered that there were serious water intrusion problems throughout the project. On January 19,
1996, HOA served a notice pursuant to former Civil Code section 1375 on Madja, the developer, setting forth its
claim for defects in the design and construction of the project. fn.
3 HOA thereafter filed this action on June 12, 1996. Wong Construction and New West were among
the defendants named in the complaint. On April 1, 1997, Wong Construction filed a cross-complaint for indemnity
against the respondent subcontractors and others.
On
September 25, 1996, HOA and Wong Construction stipulated to the appointment of John R. Griffiths as a special
master in the action to regulate the pretrial proceedings. Wong Construction subsequently conducted limited
discovery related to the three-year statute of limitations of section 338. Griffiths stayed discovery except for
the purpose of discovery on the issue of the statute of limitations. He set February 27, 1998, as the date for
respondents' motion for summary judgment on the section 338 issue and ordered that discovery be completed by
January 30, 1998. Griffiths thereafter granted the parties several extensions to complete discovery and
continued the hearing on the summary judgment motion. A hearing on the motion was held on August 19, 1998. The
trial court denied the motion.
The
parties thereafter conferred with Griffiths. On April 28, 1999, Griffiths ordered that HOA provide all parties
with a protocol for its proposed destructive testing. He further ordered that HOA complete that testing by May
15, 1999.
On
September 15, 1999, Alcal moved for summary judgment, contending that Wong Construction's cross-complaint was
barred by the 10-year statute of limitations of section 337.15. Atlas also moved for summary judgment against
Wong Construction. New West and Gonzalez filed a "joinder" in Alcal's motion. On October 5, 1999, Wong
Construction filed an ex parte application to continue the hearing on the motions of Alcal and Atlas so that its
own summary judgment motion raising the identical issue could be heard at the same time. On October 12, 1999,
the trial court continued the hearing on the motions for summary judgment to December 1, 1999, and ordered that
all motions for summary judgment that were filed by October 21, 1999 in the matter would be heard on that date.
On
October 22, 1999, HOA filed an ex parte application for a continuance of the hearing on the summary judgment
motions. It contended that it did not yet have the results of the destructive testing conducted in September and
that it was currently scheduling additional destructive testing. fn.
4 It further argued that it did not have sufficient time to review over 20 boxes of documents
in order to prepare a meaningful opposition to the motion prior to the hearing on December 1. The trial court
denied the application.
Meanwhile,
on October 29, 1999, Wong Construction served its motion for summary judgment raising the 10-year limitations
period of section 337.15 as a bar to HOA's action. New West filed a joinder in this motion.
Upon
recommendation of Griffiths, the trial court continued the hearing to January 5, 2000. On January 11, 2000, the
parties stipulated that the hearing on the summary judgment motions would be continued for 30 days. The hearing
on the motions was subsequently held on February 10, 2000. The trial court granted the motions and entered
judgments in favor of respondents, concluding that HOA's action and Wong Construction's cross-complaint against
Alcal and Atlas and "all deemed cross-complaints" were barred by the 10-year statute of limitations set forth in
section 337.15. HOA timely appeals the judgments in favor of respondents with the exception of the judgment
dismissing the action against Atlas. fn.
5 Wong Construction cross-appeals from the judgment entered on its cross-complaint.
II.
DISCUSSION
A.
Standing
fn. *
Preliminarily,
we address the contention of respondents Alcal and Gonzalez that HOA lacks standing to appeal the judgment in
their favor on Wong Construction's cross-complaint because HOA was not named in the cross-complaint. We conclude
that HOA lacks standing.
In
Salinero v. Pon (1981)
124 Cal.App.3d 120,
127-128, the court held that a plaintiff was an aggrieved party with standing to appeal a summary judgment in favor
of a cross-complainant even though he was not a party to the cross-complaint. There, the plaintiff, in a personal
injury action, was injured in a fall from an apartment building. He sued the owners of the building who in turn
cross-complained against the building's architect. The trial court entered summary judgment in favor of the
architect finding that the action was barred by the four-year statute of limitations of section 337.1.
(Salinero, at p. 127.) The Court of Appeal held that the plaintiff had standing to assert the
unconstitutionality of section 337.1 because he could have substituted the architect as a Doe defendant by amending
his complaint before the trial court granted summary judgment. "At least before summary judgment was granted,
appellant retained the option of substituting [the cross-defendant] for a doe defendant by amendment of the
complaint. The trial court's ruling thus adversely affected [plaintiff's] right to pursue his cause of action
against [the cross-defendant architect], given the application of res judicata or collateral estoppel principles to
bar any subsequent action by [plaintiff] against [cross-defendant]." (Salinero, at pp. 127-128.)
Alcal
argues that Salinero is distinguishable from the case here in that HOA cannot substitute Alcal as a Doe
defendant because the time limit for service of a complaint has expired pursuant to section 583.210. We agree.
Section
583.210, subdivision (a) provides that "[t]he summons and complaint shall be served upon a defendant within
three years after the action is commenced against the defendant. For the purpose of this subdivision an action
is commenced at the time the complaint is filed." Here, HOA filed its complaint against Wong Construction and
others on June 12, 1996. More than three years later, on September 15, 1999, Alcal filed its motion for summary
judgment while Gonzalez filed its notice of joinder in Alcal's motion on September 28, 1999. Thus, unlike the
plaintiff in Salinero, HOA was not in a position to amend its complaint "before summary judgment was
granted." (Salinero v. Pon, supra, 124 Cal.App.3d at p. 128.) Alcal is correct that any attempt by
HOA to amend its complaint to add the cross-defendants would be untimely under section 583.210.
Relying
on Fleck v. Bollinger Home Corp. (1997)
54 Cal.App.4th 926,
HOA argues that it nevertheless has standing because it could have accepted an assignment of Wong Construction's
claims in the cross-complaint against Alcal. In Fleck, a construction defects action, the trial court
granted the developer's motion for summary judgment on the plaintiff's claim on the ground that it was barred by
the 10-year statute of limitations of section 337.15. Thereafter, the plaintiff entered into a settlement agreement
with the builder under which the builder assigned its cross-complaint for indemnity against the developer to the
plaintiff. (Fleck, at p. 929.) The defendant builder's cross-complaint was timely under an exception in
section 337.15, subdivision (c) because he was timely sued in the main action. (Fleck, at p. 932.) The
court, reasoning that the purpose of section 337.15, subdivision (c) was to ensure that the 10-year statute did not
bar a subsequent tortfeasor who is timely sued from obtaining indemnification against a previous tortfeasor, held
that it was proper to permit the subsequent tortfeasor to assign its claim to the plaintiff. (Fleck, at pp.
933-934.) "The policy in California is to permit parties to assign choses in action for wrongs done to property.
[Citations.] There is no reason why an improver of property which has a latent defect caused by a former tortfeasor
may not assign its cross-complaint for indemnity before it may be found liable for damages." (Id. at p.
932.)
Here,
however, unlike the plaintiff in Fleck, HOA did not settle its claim with Wong Construction or obtain an
assignment of Wong Construction's cross-complaint for indemnity; nor is there any indication in the record that
an assignment was pending. Hence, any discussion of an assignment here is pure speculation and is insufficient
to support a finding that HOA had standing to oppose the summary judgment motions of the cross-defendants or
that it has any standing here to appeal the judgments on those motions. (See § 902 [only aggrieved party may
appeal]; Shearer v. United California Theatres (1955)
133 Cal.App.2d 720,
722-723 [plaintiff lacked standing to appeal summary judgment entered in favor of cross-defendants in cross-action
to which she was not a party]; Stanley v. Robert S. Odell and Co. (1950)
97 Cal.App.2d 521,
523 [defendants who were not parties to the cross-complaint had no standing to appeal from the judgment on that
complaint].) We therefore dismiss HOA's appeal insofar as it purports to appeal the judgments entered in favor of
Alcal and Gonzalez on Wong Construction's cross-complaint.
B.
Joinders
fn. *
HOA
contends that the trial court erred in permitting Gonzalez and New West to file joinders in the motions filed by
Alcal and Wong Construction. While HOA lacks standing to challenge Gonzalez's joinder in Alcal's motion, New
West's joinder in Wong Construction's motion did not violate section 437c, subdivision (b). That joinder
contained a memorandum of points and authorities and a separate statement of undisputed material facts. New West
thus complied with section 437c, subdivision (b).
Although
Gonzalez's joinder simply incorporated by reference the points and authorities and separate statement filed by
Alcal, Wong Construction does not contest the propriety of the joinder on appeal and did not object to the
joinder in the trial court. Despite procedural irregularities in the joinder of Gonzalez, the trial court did
not err in considering the motions inasmuch as the same facts were germane to all the motions. Moreover, it
would have constituted a substantial waste of time and judicial resources to require the parties to submit to
further proceedings. (See Fieldstone Co. v. Briggs Plumbing Products, Inc. (1997)
54 Cal.App.4th 357,
372, fn. 13; but see Frazee v. Seely (2002) 95 Cal.App.4th 627, 636 [moving party's failure to comply with
the requirement that it include a separate statement of material facts in its moving papers on summary judgment
motion is grounds to deny motion].)
C.
Procedural Due Process
fn. *
HOA
contends that section 437c is unconstitutional because it does not afford a party opposing a motion for summary
judgment an adequate opportunity to prepare a response. It also argues the particular facts of this case
demonstrate that it was denied due process.
HOA
fails to demonstrate that section 437c is unconstitutional. (See Mounts v. Uyeda (1991)
227 Cal.App.3d 111,
122 [party challenging constitutionality of statute must demonstrate that its provisions pose a fatal conflict with
constitutional prohibitions].) First, its arguments that the statute ignores the realities of litigation are
feckless. fn.
6 Second, HOA has failed to show that it was denied any due process in this action. Wong
Construction's motion for summary judgment was served on October 29, 1999, with a hearing date of December 1, 1999.
However, by stipulation, the hearing was continued and ultimately held on February 10, 2000. Thus, although the
statute normally allows about two weeks to prepare and file an opposition, HOA did not file its opposition to the
motion until January 27, 2000, three months after the motion was served. Moreover, HOA did not submit an affidavit
seeking a continuance to develop additional facts in opposition to the motion. (§ 437c, subd. (h).) Under these
circumstances, HOA is not in a position to claim that its due process rights were violated or that it had
inadequate time in which to respond to Wong Construction's motion.
D.
Section 337.15
1.
Equitable tolling
HOA
contends that section 337.15 was tolled during the period in which respondents repaired defects in the
construction of the project. This contention has merit.
Section
337.15 establishes a 10-year statute of limitations for actions to recover damages based on latent construction
defects. In pertinent part, section 337.15 provides: "(a) No action may be brought to recover damages from any
person . . . who develops real property or performs or furnishes the design, specifications, surveying,
planning, supervision, testing, or observation of construction or construction of an improvement to real
property more than 10 years after the substantial completion of the development or improvement for any of
the following: [¶] (1) Any latent deficiency in the design, specification, surveying, planning, supervision, or
observation of construction or construction of an improvement to, or survey of, real property." (Italics added.)
The
issue of whether the 10-year statute of limitations of section 337.15 is subject to equitable tolling during
periods of repair is currently before our Supreme Court in Lantzy v. Centex Homes (2001)
89 Cal.App.4th 1059,
review granted August 22, 2001, S098660. Several courts have held, however, that in construction defect actions,
the statute of limitations is tolled during periods in which the defendant attempts to repair the defect. (Aced
v. Hobbs-Sesack Plumbing Co. (1961)
55 Cal.2d 573,
585 ["statute of limitations is tolled where one who has breached a warranty claims that the defect can be repaired
and attempts to make repairs"]; Grange Debris Box & Wrecking Co. v. Superior Court (1993)
16 Cal.App.4th 1349,
1360 [recognizing that section 337.15 is tolled for periods of repair]; Cascade Gardens Homeowners Assn. v.
McKellar & Associates (1987)
194 Cal.App.3d 1252,
1256 and cases cited therein; 3 Witkin, Cal. Procedure (4th ed. 1996) Actions, § 684, p. 871.) "Tolling during a
period of repairs rests upon the same basis as does an estoppel to assert the statute of limitations, i.e.,
reliance by the plaintiff upon the words or actions of the defendant that repairs would be made." (A & B
Painting & Drywall, Inc. v. Superior Court (1994)
25 Cal.App.4th 349,
355.)
In
Cascade Gardens Homeowners Assn. v. McKellar & Associates, supra, 194 Cal.App.3d at page 1256,
the homeowners association filed its action for defective construction 10 years and 1 month after the date the
notice of completion was recorded. The court held that the statute of limitations was tolled during a four-month
period in which the developer made repairs to correct roof leaks. (Id. at pp. 1257-1258.)
In
A & B Painting & Drywall, Inc. v. Superior Court, supra, 25 Cal.App.4th at page 355, this
court held that repairs undertaken by someone other than the original entity that did the original work did not
toll the section 337.15 limitations period. There, approximately seven months before the running of the 10-year
statute, the developer retained a contractor to repair the interior drywall framing of the Hillsdale Mall. (A
& B Painting, at pp. 353, 355.) We declined to extend Cascade to toll the limitations period on
the developer's action against the contractor, reasoning that repairs by the contractor, a third party that was
not originally responsible for the defect, did not involve reliance on the entity which warranted the original
work and thus did not furnish a basis for tolling. (A & B Painting, at pp. 354-355.) We also rejected
a claim that work done in 1982, the year following the filing of the notice of completion, tolled the 10-year
statute because the developer failed to show that the repair work included any of the developer's present
complaints. fn.
7 (Id. at p. 356.)
In
FNB Mortgage Corp. v. Pacific General Group (1999)
76 Cal.App.4th 1116,
1134 (FNB Mortgage), the court held that section 337.15 is not subject to equitable tolling for repairs. The
court distinguished the 10-year limitations period of section 337.15 from other limitations statutes, stating that
section 337.15 establishes an outside limit for actions against a contractor for latent defects. (FNB
Mortgage, at p. 1131.) It reasoned that the purpose of the statute was to " 'protect contractors and other
professionals and tradespeople in the construction industry from perpetual exposure to liability for their work . .
.' [citation]" and that equitable tolling of the statute for repairs would run afoul of this purpose. (Id.
at pp. 1132-1133.)
We
disagree with the holding of FNB Mortgage. As the Supreme Court acknowledged in Regents of University
of California v. Hartford Acc. & Indem. Co. (1978)
21 Cal.3d 624,
642, "section 337.15 [is] an ordinary statute of limitations, subject to the same rules . . . as other statutes of
limitations." One of these rules, equitable tolling of a limitations statute for periods of repair, is well
established. (Cascade Gardens Homeowners Assn. v. McKellar & Associates, supra, 194 Cal.App.3d at
p. 1256.) Further, permitting tolling of the limitations statute during periods of repair does not frustrate the
purpose of section 337.15. To the contrary, a contractor cannot be deemed to be surprised by a claim for a
construction defect when it has been put on notice that a problem exists by virtue of its attempt to repair the
problem during the limitations period. The purpose of a limitations statute is to " '[prevent] surprises through
the revival of claims that have been allowed to slumber until evidence has been lost, memories have faded, and
witnesses have disappeared.' [Citations.]" (Elkins v. Derby (1974)
12 Cal.3d 410,
417, fn. omitted.) Nor are contractors subject to perpetual exposure to liability as a result of our holding. We
presume that in most cases, as in the case here, the period of repair will be of relatively short duration and thus
will not unduly extend the statutory period.
Moreover,
the facts of FNB Mortgage are clearly distinguishable from those here. There, FNB entered into an
agreement with the plaintiff to toll the limitations period. FNB, however, did not protect itself by entering
into a similar agreement with Pacific General, the developer with which it contracted to construct an apartment
complex. (FNB Mortgage, supra, 76 Cal.App.4th at pp. 1121-1122, 1124.) While the plaintiff's
underlying action was timely due to the tolling agreement, FNB's cross-complaint was barred because it was filed
after the expiration of the 10-year limitations period. (Id. at p. 1135.) The court determined that any
promises by Pacific General to the plaintiff to repair defects in the complex had no effect on whether FNB chose
to file suit as it would not have induced FNB's reliance to delay the filing of its cross-complaint.
(Ibid.) "It was in FNB's control whether plaintiff's action was filed within the 10-year period, and it
chose to extend the time for plaintiff, while doing nothing to protect its right to bring its own claim for
indemnity. A contractor or subcontractor, whether suspecting or unsuspecting, does not lose the protections of
the 10-year limitations period under section 337.15 because of the conduct of another party that extends
the time for suit against itself." (Ibid.)
Here,
HOA presented evidence in its opposition to Wong Construction's summary judgment motion that Wong Construction
engaged in significant repair work during 1986, and as late as December 3, 1986, relating to the water leakage
problems that resulted in the present action. In contrast to FNB Mortgage, there is evidence that HOA
relied on Wong Construction's promises to repair the defects during this period. Indeed, as noted in TAA's
letter dated December 3, 1986 to Wong Construction, "[w]e are hoping that, by completing these items [including
repairs to areas affected by water leakage] as soon as possible, we will delay the Homeowners from taking legal
action before the end of the year." This evidence at the very least raises a triable issue of fact supporting
HOA's position that the 10-year statute was tolled during some part of 1996 on HOA's complaint against Wong
Construction, in which case HOA's action, filed on June 12, 1996, may well have been timely. The resolution of
this issue requires a full evidentiary hearing in the trial court in which the parties can address whether the
evidence proffered by HOA establishes that repairs related to the defects alleged in the complaint were made
after the filing of the notice of completion, and if so, for what period the statute was tolled.
HOA,
however, did not show that New West made any repairs during the 10-year period following the filing of its
complaint. (See A & B Painting & Drywall, Inc. v. Superior Court, supra, 25 Cal.App.4th at
pp. 354-355 [limitations period will not be tolled for entity that does not undertake repairs].) Nor did it
submit any evidence that New West engaged in any willful misconduct such that the action would fall within the
exception to the 10-year period for actions based on willful misconduct or fraudulent concealment. fn.
8 (§ 337.15, subd. (f).) Given these omissions, we will affirm the summary judgment entered in
favor of New West on HOA's complaint.
2.
Controlling date
fn. *
If
HOA is able to show that the limitations period was equitably tolled due to repairs, the trial court will be
required to determine the applicable dates for the commencement of the 10-year period and the date(s) of its
tolling. In calculating the limitations period, HOA contends that the controlling date is the date on which it
served a Calderon notice on Madja, January 19, 1996, rather than October 25, 1995, 10 years from the date the
notice of completion was recorded. While a Calderon notice under Civil Code section 1375, subdivision (b)(3)(A)
extends the 10-year limitations period of section 337.15 for an additional 150 days, we conclude that HOA's
action filed June 12, 1996, was timely only if the limitations period was tolled for repairs for the period
between October 25, 1995, 10 years from the date the project was substantially complete, and January 19, 1996.
a.
Substantial completion
Subdivision
(g) of section 337.15 defines the term substantial completion: "The 10-year period specified in subdivision (a)
shall commence upon substantial completion of the improvement, but not later than the date of one of the
following, whichever first occurs: [¶] (1) The date of final inspection by the applicable public agency. [¶] (2)
The date of recordation of a valid notice of completion. [¶] (3) The date of use or occupation of the
improvement. [¶] (4) One year after termination or cessation of work on the improvement. [¶] The date of
substantial completion shall relate specifically to the performance or furnishing design, specifications,
surveying, planning, supervision, testing, observation of construction or construction services by each
profession or trade rendering services to the improvement."
HOA
contends that the notice of completion was invalid because the project was not substantially complete on October
26, 1985. It relies on several cases in which the courts have considered whether a party substantially performed
its contractual obligations. (See, e.g., Tolstoy Const. Co. v. Minter (1978)
78 Cal.App.3d 665;
Thomas Haverty Co. v. Jones (1921) 185 Cal. 285.) HOA's reliance on the doctrine of substantial performance
is misplaced.
As
Wong Construction points out, there is no need to construe the meaning of the term substantial completion
because it is defined in section 337.15. Subdivision (g) of section 337.15 defines the events that constitute
substantial completion of an improvement and thus start the running of the limitations period. The recording of
a valid notice of completion is one of those events. fn.
9 (§ 337.15, subd. (g)(2); A & B Painting & Drywall, Inc. v. Superior Court,
supra, 25 Cal.App.4th at p. 356 [notice of completion is event that commences the 10-year statute of
limitations].)
"If
the statute's language is clear and unambiguous, there is no need for construction, nor is it necessary to
resort to indicia of the intent of the Legislature." (Schwetz v. Minnerly (1990)
220 Cal.App.3d 296,
302.) We nonetheless note that the Legislature set forth its objective in enacting subdivision (g) of section
337.15 in the Legislative Counsel's Digest as follows: " 'Under existing law, an action for damages for or arising
from a latent deficiency against persons who develop real property or who perform various services relative to the
construction of improvements on real property may be barred after 10 years following substantial completion of the
particular development or work of improvement. Existing law does not define the term "substantial completion." [¶]
This bill would define the term "substantial completion." ' " (Schwetz, at pp. 306-307.) Hence, under
section 337.15, Madja's recording of the notice of completion on October 26, 1985, triggered the commencement of
the 10-year statute of limitations.
b.
Civil Code section 1375
If
HOA establishes equitable tolling of the limitations period between October 25, 1995, and the filing of the
Calderon notice on January 19, 1996, for a period of at least 86 days, HOA's compliance with the provisions of
Civil Code section 1375 would extend the limitations period for an additional 150 days. fn.
10 Under this scenario, HOA's action filed June 12, 1996, would be timely.
3.
Willful misconduct
fn. *
If
HOA is unable to establish equitable tolling below, we conclude that it cannot rely on the willful misconduct
exception to section 337.15. Under subdivision (f) of section 337.15, the 10-year statute does not apply to
actions based on willful misconduct or fraudulent concealment.
"The
term 'willful misconduct' as used in the statute encompasses not only intentional wrongdoing, but negligence of
such a character as to constitute reckless disregard for the rights of others." (Felburg v. Don Wilson
Builders (1983)
142 Cal.App.3d 383,
391.) "Three elements are necessary to raise a negligent act to the level of willful misconduct: actual or
constructive knowledge of the peril to be apprehended; actual or constructive knowledge that injury is a probable
as opposed to a possible result of the danger; and a conscious failure to act to avert that peril." (Colich
& Sons v. Pacific Bell (1988)
198 Cal.App.3d 1225,
1242.)
In
Felburg v. Don Wilson Builders, supra,
142 Cal.App.3d 383,
plaintiff homeowners sued a developer for willful misconduct and fraudulent concealment after discovering that the
subsidence of their house was due to the fact that it was built over an old oil sump. The court concluded that
there were triable issues of fact on the issue of whether the willful misconduct exception to section 337.15
applied. The court determined that the developer failed to refute the plaintiffs' expert's declaration that opined,
"it would have been impossible to pour the foundation of the home without seeing the evidence, in plain view, that
the lot was over an oil sump. The evidence was so clear . . . that 'it makes me of the opinion that there was a
conscious effort to ignore this condition.' " (Felburg, at pp. 390, 392.) The court held that the expert's
declaration, in addition to other evidence presented by the plaintiffs, suggested sufficient grounds for trial on
the merits of whether the developer knew of the presence of the oil sump and possibly concealed it with fraudulent
intent. (Id. at p. 392.)
Here,
HOA relies on the declaration of Adam Posard to establish the three elements of willful misconduct. The Posard
declaration alleged that Uniform Building Code (UBC) requirements for fire resistive construction were violated.
In particular, he alleged that installation of plumbing, mechanical and ventilation duct penetrations into the
firewalls of the project were not fire resistive. Posard further stated that Wong Construction, Atlas and F. W.
Spencer & Son, Inc. (F. W. Spencer) fn.
11 knew of the UBC requirements, that their solution to correct the structural problem failed
to remedy it, that they should have known that the duct penetrations placed the project's occupants at risk in
the event of a fire, and that they consciously acted to leave the duct penetrations unprotected. fn.
12
Unlike
the evidence proffered in Felburg v. Don Wilson Builders, supra, 142 Cal.App.3d at pages 390, 392,
Posard's declaration does not establish that the contractors willfully acted to violate UBC requirements related
to firewall construction or that they sought to conceal the possible code infractions. To the contrary, the
declaration cites to evidence of correspondence among Wong Construction, TAA, and F. W. Spencer in which they
sought to remedy the problem. According to this evidence, TAA and a structural engineer stopped F. W. Spencer
from proceeding to install the plumbing and sheet metal in the project and cutting any studs or any wood
members. F. W. Spencer informed Wong Construction of the stop order and requested that space be designed to
accommodate the plumbing, piping, and sheet metal ducts.
Atlas,
in turn, notified F. W. Spencer of its problems with insufficient space for its heating, exhaust and flue duct
work on the project. In order to resolve these problems, changes were made to the framing on the third and upper
floors of the project to accommodate the mechanical and plumbing piping and duct work. The walls were "furred"
to accommodate the pipe work.
Other
than Posard's conclusory opinion in his declaration that the actions of Wong Construction, F. W. Spencer and
Atlas, in making duct penetrations without including the fire stopping as required by the UBC, amounted to
willful misconduct, there is no evidence to support that opinion. fn.
13 Rather, the evidence shows that the contractors made efforts to correct the design and
construction of the firewalls. To the extent that Posard is correct that duct penetrations made by the
mechanical and plumbing subcontractors were not fire resistive in compliance with the UBC, there is insufficient
evidence to show that the omission was done in conscious disregard of a probability of damage due to fire. The
evidence, at most, raises an issue as to whether the contractors were negligent in constructing the firewalls.
Under these circumstances, the trial court properly determined that the willful misconduct exception to section
337.15 was inapplicable.
E.
Wong Construction's Cross-appeal
fn. *
The
trial court granted summary judgment on Wong Construction's cross-complaint for equitable indemnity against the
subcontractors, ruling that it was barred by the 10-year limitations period of section 337.15. We affirm the
court's judgment in favor of subcontractors Alcal, Atlas and New West. Even if HOA establishes that its
complaint was not time-barred, there is no evidence in the record that those subcontractors performed any
repairs that would support equitable tolling of the limitations period on the cross-complaint. (See A & B
Painting & Drywall, Inc. v. Superior Court, supra, 25 Cal.App.4th at pp. 354-355 [limitations period
will not be tolled for repairs undertaken by an entity that did not do the original work].)
Although
section 337.15, subdivision (c) permits an indemnity cross-complaint to be filed beyond the 10-year limitations
period if the underlying action was timely filed (Valley Circle Estates v. VTN Consolidated, Inc.
(1983)
33 Cal.3d 604,
609; Fleck v. Bollinger Home Corp., supra, 54 Cal.App.4th at pp. 931-932), the exception applies only
when the action was timely under subdivision (a) of the statute. Subdivision (c) provides that an " 'action'
includes an action for indemnity brought against a person arising out of that person's performance or furnishing of
services or materials referred to in this section, except that a cross-complaint for indemnity may be filed
pursuant to subdivision (b) of Section 428.10 in an action which has been brought within the time period set forth
in subdivision (a) of this section." (Italics added.) This language means "that a cross-complaint for indemnity
may be filed more than 10 years after the alleged indemnitor has substantially completed his services, provided
that the underlying action was itself brought within the 10-year limitation period of the statute. [¶] Thus, a
defendant timely sued under section 337.15, subdivision (a), may file under subdivision (c) a cross-complaint for
indemnity against a third party who could not otherwise be reached by a direct action for indemnity filed by the
defendant, or by a direct suit for damages filed by the plaintiff." (Valley Circle Estates v. VTN Consolidated,
Inc., supra, 33 Cal.3d at p. 609.) This statutory language precludes the cross-complaint against subcontractors
Alcal, Atlas and New West here. The cross-complaint, filed on April 1, 1997, was filed more than 10 years after the
notice of the completion and was therefore not timely under subdivision (a) of section 337.15. As there is no
evidence that these subcontractors performed any repairs to toll the limitations period of subdivision (a), the
cross-complaint is barred under section 337.15.
There
is, however, evidence in the record that Gonzalez may have performed repairs after the notice of completion was
filed. Until the timeliness of HOA's complaint against Wong Construction is determined--which, as we have
already noted, is an issue of fact--the exception under section 337.15, subdivision (c) forecloses the argument
of Gonzalez that the cross-complaint is barred by the 10-year limitations period. If HOA's complaint against
Wong Construction is timely, there is a triable issue of fact as to whether Wong Construction's cross-complaint
for indemnity as against Gonzalez is also timely due to equitable tolling. The trial court's order granting
summary judgment on the cross-complaint against Gonzalez must therefore be reversed.
F.
Attorney Fees
fn. *
The
trial court awarded Alcal, Atlas, New West and Gonzalez attorney fees based on provisions in their subcontracts
with Wong Construction providing that fees be awarded to the prevailing party. On our own motion, we
consolidated Wong Construction's appeal from the court's orders on fees with the underlying appeals from the
judgments. We reverse the order entered on Gonzalez's motion for attorney fees but otherwise affirm the orders
granting fees. fn.
14
Civil
Code section 1717, subdivision (a) provides that "[i]n any action on a contract, where the contract specifically
provides that attorney's fees and costs, which are incurred to enforce that contract, shall be awarded either to
one of the parties or to the prevailing party, then the party who is determined to be the party prevailing on
the contract . . . shall be entitled to reasonable attorney's fees in addition to other costs." The party
prevailing on the contract is "the party who recovered a greater relief in the action on the contract."
(Id., subd. (b)(1).) "We will not disturb the trial court's determination of the prevailing party absent
a clear abuse of discretion." (Sears v. Baccaglio (1998)
60 Cal.App.4th 1136,
1158.)
Wong
Construction contends that the trial court abused its discretion in awarding fees pursuant to Civil Code section
1717 because none of the subcontractors prevailed on the contract. It argues that the court's ruling in the
subcontractors' favor on their summary judgment motions based on the statute of limitations defense was not a
determination that they prevailed on the contract. We cannot agree.
It
is well settled that a party is entitled to fees under Civil Code section 1717 " 'even when the party prevails
on grounds the contract is inapplicable, invalid, unenforceable or nonexistent, if the other party would have
been entitled to attorney's fees had it prevailed.' " (Hsu v. Abbara (1995)
9 Cal.4th 863,
870.) "The statute would fall short of [its] goal of full mutuality of remedy if its benefits were denied to
parties who defeat contract claims by proving that they were not parties to the alleged contract or that it was
never formed." (Ibid.) Similarly, this goal would be defeated if recovery of fees was denied to a party
prevailing in the action on procedural grounds. (See Elms v. Builders Disbursements, Inc. (1991)
232 Cal.App.3d 671,
674-675 [party that obtained dismissal of an action when plaintiff failed to bring it to trial within five years
was prevailing party entitled to recover fees under Civil Code section 1717]; see also Wong v. Thrifty Corp.
(2002) 97 Cal.App.4th 261 [lessor entitled to fees under Civil Code section 1717 in action where lessor accepted
lessee's section 998 offer to compromise].)
Here,
the subcontractors were the prevailing parties on Wong Construction's cross-complaint for indemnity under the
contracts between the parties. The subcontracts contained the following attorney fees provision: "In the event
either CONTRACTOR or SUBCONTRACTOR institutes suit in court against the other party, or against the surety of
such party, in connection with any dispute or matter arising under this Agreement, the party which prevails in
that suit shall be entitled to recover from the other its attorney's fees in reasonable amount, which shall be
determined by the court and included in the judgment in said suit." Wong Construction's contention that the
subcontractors did not prevail on the contracts because their summary judgment motions were granted based on the
statute of limitations defense rather than the merits of a contract claim is nonsensical and unsupported by any
pertinent authority. fn.
15 The subcontractors prevailed on the contracts through their respective summary judgment
motions. (Hsu v. Abbara, supra, 9 Cal.4th at p. 870.) They were thus prevailing parties on the
subcontracts within the meaning of Civil Code section 1717.
Wong
Construction also contends that Civil Code section 1717 applies only to attorney fees incurred to litigate
contract claims. The language of the fee provision refutes this contention.
"If
a contractual attorney fee provision is phrased broadly enough . . . it may support an award of attorney fees to
the prevailing party in an action alleging both contract and tort claims: '[P]arties may validly agree that the
prevailing party will be awarded attorney fees incurred in any litigation between themselves, whether such
litigation sounds in tort or in contract.' [Citation]" (Santisas v. Goodin (1998)
17 Cal.4th 599,
608.) Whether a contractual provision for attorney fees authorizes fees for a tort cause of action depends on the
intent of the parties. (Allstate Ins. Co. v. Loo (1996)
46 Cal.App.4th 1794,
1798.) That intent is inferred, if possible, from the written provisions of the contract. (Ibid.; see also
Santisas v. Goodin, supra, 17 Cal.4th at p. 608.)
The
attorney fees provisions in the subcontracts between the parties provide for an award of fees "in connection
with any dispute or matter arising under this Agreement . . . ." The parties thus agreed that the prevailing
party would be awarded fees whether the litigation related to contract or noncontract claims, or both.
(Santisas v. Goodin, supra, 17 Cal.4th at p. 608.) In light of the broad language of the fees
provision, the trial court did not abuse its discretion to the extent it awarded fees for noncontract claims.
Finally,
Wong Construction contends that the fees awarded were excessive and not supported by the record. The record,
however, contains abundant evidence supporting the fee awards.
An
award of attorney fees rests within the sound discretion of the trial court and will not be disturbed on appeal
absent a manifest abuse of discretion, for example, where the amount of the award is "so large or small that it
shocks the conscience and suggests passion and prejudice influenced the determination." (Niederer v.
Ferreira (1987)
189 Cal.App.3d 1485,
1507.) In making its determination, the trial court considers a number of factors including "the necessity for and
the nature of the litigation, the amount involved, and the success or failure of the attorney's efforts, including
the amount of recovery." (Kanner v. Globe Bottling Co. (1969)
273 Cal.App.2d 559,
569.) Based on a consideration of various factors, the trial court may rely on its own expertise and knowledge to
calculate reasonable attorney fees. (Niederer v. Ferreira, supra, 189 Cal.App.3d at p. 1507.) The
court is not limited to the affidavits submitted by the attorney (Melnyk v. Robledo (1976)
64 Cal.App.3d 618,
625) and may award attorney fees in excess of the hourly calculation provided by the attorney (City of Oakland
v. Oakland Raiders (1988)
203 Cal.App.3d 78,
85).
Here,
the subcontractors provided ample documentation of the attorney fees incurred through the declarations of
counsel and billing records, and there is no indication that the fees were inflated or unusually large. (Cf.
Martino v. Denevi (1986)
182 Cal.App.3d 553,
559-560 [evidence insufficient to support fee award where the only evidence presented was the attorney's request
for a flat fee].) There is simply nothing in the record to suggest that the fees awarded were unreasonable. The
value of legal services is a matter within the trial court's expertise. (Melnyk v. Robledo, supra, 64
Cal.App.3d at p. 623.) On the record before us, we conclude that the trial court did not abuse its discretion in
its awards of fees to the subcontractors.
III.
DISPOSITION
HOA's
purported appeals of the summary judgments entered in favor of Alcal (A091787) and Gonzalez (A092084) are
dismissed. The judgment entered in favor of New West on HOA's complaint (A092537) is affirmed, as is the
judgment entered in favor of New West on Wong Construction's cross-complaint (A092000). The judgments in favor
of Wong Construction and Gonzalez in A092062 are reversed. In all other respects, the judgments in A092062 are
affirmed. The order awarding Gonzalez attorney fees in A092730 is reversed. The remaining orders in A092730 are
affirmed, with costs to Alcal, Atlas and New West. The parties are to bear their own costs on all other appeals.
Kay,
P. J., and Reardon, J., concurred.
FN *. Jackson
Plaza Homeowners Assn. v. New West Roofing, Inc. (No. A092000); Jackson Plaza Homeowners Assn. v. W. Wong
Construction (No. A092062); Jackson Plaza Homeowners Assn. v. Gonzalez Roofing & Waterproofing Co.
(No. A092084); Jackson Plaza Homeowners Assn. v. New West Roofing, Inc. (No. A092537); W. Wong
Construction v. Alcal Roofing and Insulation (No. A092730).
FN †. Pursuant
to California Rules of Court, rules 976(b) and 976.1, this opinion is certified for publication with the exception
of parts II.A. through II.C., II.D.2., II.D.3., II.E. and II.F.
FN 1. Unless
otherwise indicated, all further statutory references are to the Code of Civil Procedure.
FN 2. Throughout
its recitation of the facts and procedural background in its opening brief, HOA purports to set forth a chronology
of the case but in numerous instances fails to cite to any evidence in the record to support its facts. It is well
settled that a party is required to support the statement of any matter in the record by an appropriate reference
to the record. (Cal. Rules of Court, rule 14(a)(1).) To the extent that HOA fails to support its facts with
references to the record, we have disregarded its assertions. (Goodstein v. Cedars-Sinai Medical Center
(1998)
66 Cal.App.4th 1257,
1260, fn. 1.)
FN 3. The
parties refer to this notice as the "Calderon" notice. Senator Charles M. Calderon drafted Senate Bill No. 1029
which was subsequently enacted as Civil Code section 1375. (Stats. 1995, ch. 864, § 1, No. 11 West's Cal. Legis.
Service, pp. 5117-5121.) Subsequent references to Civil Code section 1375 will refer to the version in effect at
the time of service of the Calderon notice.
FN 4. HOA
conducted destructive testing on September 28 and 29, 1999.
FN 5. In
its reply brief, HOA explains that it failed to appeal the Atlas judgment as "a result of the confusion created by
the multiple orders and judgments."
FN *. See
footnote, ante, page 1.
FN *. See
footnote, ante, page 1.
FN *. See
footnote, ante, page 1.
FN 6. For
example, HOA claims that the statute is "based on the legislative assumption that litigation attorneys do not have
lives."
FN 7. In
dicta, we noted that had the defects been discovered in 1982, they "would have triggered a shorter period of time
in which to bring suit because the defects would then have been patent, rather than latent, and the four-year
statute to bring an action on a patent defect would have applied. (§ 337.1.)" (A & B Painting & Drywall,
Inc. v. Superior Court, supra, 25 Cal.App.4th at p. 357.)
FN 8. In
its opening brief, HOA states that it introduced evidence in its opposition to the summary judgments showing that
Wong Construction and Atlas committed willful misconduct. HOA makes no reference to New West.
FN *. See
footnote, ante, page 1.
FN 9. HOA
has not shown that the notice of completion was invalid. (See Civ. Code, § 3093 [setting forth the requirements for
a notice of completion]; see also Eden v. Van Tine (1978)
83 Cal.App.3d 879,
885 [notice of completion constituted substantial completion where there was no evidence produced by plaintiffs
that the notice was invalid].)
FN 10. The
Calderon notice tolls "all statutory and contractual limitations on actions against all parties who may be
responsible for the defects claimed, whether named in the notice or not, including claims for indemnity applicable
to the claim, for a period of 150 days or a longer period agreed to in writing by the association and the builder."
(Civ. Code, § 1375, subd. (b)(3)(A).) It, however, does not toll an applicable limitations period that has already
expired. Thus, if HOA is unable to establish equitable tolling of the 10-year limitations period to the time of the
Calderon notice, its service of the notice upon Madja was of no avail.
FN *. See
footnote, ante, page 1.
FN 11. F.
W. Spencer is a plumbing and heating contractor that worked on the project. It is named as a cross-defendant in
Wong Construction's cross-complaint but it did not move for summary judgment and is not a party to these appeals.
FN 12. Wong
Construction objected to the Posard declaration on the grounds that Posard was not qualified to offer a legal
opinion, and that his statements were speculative and lacked foundation. The trial court agreed that the evidence
lacked competence and was inadequate to support the evidence of willful misconduct. We agree that the declaration
is inadequate, and thus need not reach the other evidentiary objections raised by Wong Construction in the trial
court.
FN 13. Nor
does Posard refer to the relevant UBC provisions that the contractors allegedly violated.
FN *. See
footnote, ante, page 1.
FN *. See
footnote, ante, page 1.
FN 14. Since
we reverse the summary judgment entered in favor of Gonzalez on Wong Construction's cross-complaint, the trial
court's postjudgment order awarding Gonzalez fees as the prevailing party must also be reversed.
FN 15. Lackner
v. LaCroix (1979)
25 Cal.3d 747 and
Warren v. Wasserman, Comden & Casselman (1990)
220 Cal.App.3d 1297,
cited by Wong Construction for the proposition that the termination of an action by a statute of limitations
defense is a technical or procedural termination as opposed to a substantive termination, are not on point. Those
cases involved the question of whether a successful statute of limitations defense in an underlying action is a
favorable termination for purposes of a subsequent malicious prosecution action. They did not address the question
presented here of whether a party that succeeds on a summary judgment motion based on a statute of limitations
defense is a prevailing party on a contract within the meaning of Civil Code section 1717.
|